Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
Tools
- Court
- Supreme Court of India
- Decided
- Bench
- B. R. Gavai (author) and Prashant Kumar Mishra
- Citation
- [2024] 1 S.C.R. 909 : 2024 INSC 23
Source PDF (original scan)
Contains information from the Indian High Court / Supreme Court Judgments dataset, licensed under CC-BY-4.0
Headnote — Supreme Court Reports (editorial summary, not part of the judgment)
Issue for consideration
State Commission held that the tariffs offered by the L-4 and L-5 bidders were not aligned to the prevailing market prices. In appeal by L-5, APTEL held that the State Commission had to necessarily adopt the tariff and had no power to consider whether the tariff was aligned to market prices. Impugned judgment of the High Court relying on the said judgment of the APTEL and the earlier orders of this Court concluded that applying the test of “filling the bucket”, the procurers were bound to take supply from the respondent No.1 at the rates quoted by it and it had a right to supply power since there was a gap of 300 MW between the power procured by the procurers and the ceiling of 906 MW determined by this Court. High Court whether justified in issuing mandamus directing the appellants to take supply of 200 MW power from the respondent No.1 at the rates quoted by it. Power of the State Commission to go into the question as to whether the prices quoted are market aligned or not and to take into consideration the aspect of consumers’ interest.
Catchwords
Digital Supreme Court Reports vide order dtd.19.11.18, State Commission was directed to go into the issue of adoption of tariff – State Commission held that the tariffs offered by the L-4 and L-5 bidders were not aligned to the prevailing market prices – Appeal filed by L-5 bidder, allowed by APTEL – Writ petition was filed by the respondent No.1 – Allowed by impugned judgment:
Held
Unlike s.62 r/w ss.61 and 64, under the provisions of s.63, the appropriate Commission does not “determine” tariff but only “adopts” tariff already determined u/s.63 – Such “adoption” is only if such tariff has been determined through a transparent process of bidding, and this transparent process of bidding must be in accordance with the guidelines issued by the Central Governments – s.86(1)(b) gives ample power to the State Commission to regulate electricity purchase and procurement process of distribution licensees – It also empowers the State Commission to regulate the matters including the price at which electricity shall be procured from the generating companies, etc. – Further, orders relied upon by the APTEL, specifically the order dtd. 19.11.2018, clarified that the State Commission was to decide the tariff u/s.63 having regard to the law laid down both statutorily and by this Court – As such, the State Commission was bound to take into consideration the Bidding Guidelines notified by the Central Government, and specifically clause 5.15 thereof – State Commission justified in considering the Clause 5.15 of the Bidding Guidelines which specifically permits to reject all price bids if the rates quoted are not aligned to the prevailing market prices – APTEL grossly erred in holding that the State Commission has no power to go into the question, as to whether the prices quoted are market aligned or not and also not to take into consideration the aspect of consumers’ interest – It cannot be read from the orders of this Court that the State Commission was bound to accept the bids as quoted by the bidders till the bucket was filled – No such direction can be issued by this Court de hors the provisions of ss.63 and 86(1)(b) and the Bidding Guidelines – Since the decision-making process adopted by the Bid Evaluation Committee approved by the State Commission, was in accordance with the law laid down by this Court, the same ought not to have been interfered with by the APTEL – High Court could not have issued a mandamus to the instrumentalities of the State to enter into a contract harmful to the public interest inasmuch as, if the power was to be procured by the procurers at the rates quoted by the respondent No.1, which was even higher than the rates quoted by the L-5 bidder, then the
Catchwords
State would have to bear financial burden in thousands of crore rupees, which in turn would have passed on to the consumers – Impugned judgment quashed and set aside – Cost imposed. [Paras 67, 71, 73-75, 78, 83, 104, 105] Electricity – Competitive Bidding Guidelines notified by the Government of India u/s.63 – Respondent No.1 contended that the procurer is bound to accept all the bids emerged in a competitive bidding process once the bidding process was found to be transparent and in compliance with the Bidding Guidelines:
Held
If the contention is to be accepted it will do complete violence to clause 5.15 of the Bidding Guidelines itself – If that view is accepted, the DISCOMS will be compelled to purchase electricity at a much higher rate as compared with other suppliers – The said higher rate will be passed on to the consumers – As such, accepting the contention of the respondent No.1 would result in adversely affecting the interests of the consumers and, in turn, would be against the larger public interest. [Para 77]
Catchwords
Electricity Act, 2003 – s.63 – General Clauses Act – s.13(2) – “all”, “any” – Principle of literal interpretation – Principle of purposive construction – “all” used in clause 5.15 of the Bidding Guidelines r/ws.86(1)(b) – Competitive Bidding Guidelines notified by the Government of India u/s.63 – It was contended that the power under clause 5.15 of the Bidding Guidelines can be exercised only when the bidding process is found to be not in compliance with the Bidding Guidelines and is not transparent in respect of all the bidders and not in respect of some of the bidders is concerned:
Held
The contention is without substance – Words “all” or “any” will have to be construed in their context taking into consideration the scheme and purpose of the enactment – What is the meaning which the legislature intended to give to a particular statutory provision has to be decided by the Court on a consideration of the context in which the word(s) appear(s) and in particular, the scheme and object of the legislation – The word “all” used in clause 5.15 of the Bidding Guidelines, read with the legislative policy for which the Electricity Act was enacted and r/ws.86(1)(b), will have to be construed to be the one including “any” – Applying the principle of literal interpretation, the evaluation committee/BEC would be entitled to reject only such of the price bids if it finds that the rates quoted
Catchwords
Digital Supreme Court Reports by the bidders are not aligned to the prevailing market prices – It does not stipulate rejection of all the bids in the bidding process – If the contention that clause 5.15 of the Bidding Guidelines will come into play, which permits the Evaluation Committee to reject “all” price bids and not “any” one of them is accepted, it will lead to absurdity – The Court, while interpreting a particular provision, will have to apply the principles of purposive construction – Such an interpretation would result in defeating one of the main objects of the enactment, i.e., protection of the consumer. [Paras 84, 87, 88 and 91] Interpretation of Statutes – Principle of purposive construction – Discussed. Electricity Act, 2003 – ss.62, 63, 79(1)(b):
Held
The non-obstante clause advisedly restricts itself to s.62, there is no reason to put s.79 out of the way altogether – Either u/s.62, or 63, the general regulatory power of the Commission u/s.79(1)(b) is the source of the power to regulate, which includes the power to determine or adopt tariff – ss.62 and 63 deal with “determination” of tariff, which is part of “regulating” tariff – In a situation where the guidelines issued by the Central Government u/s.63 cover the situation, the Central Commission is bound by those guidelines and must exercise its regulatory functions, albeit u/s.79(1)(b), only in accordance with those guidelines. [Para 68]
Catchwords
Alternate remedy – Electricity Act, 2003 – Constitution of India – Article 226 – Judicial review – Scope:
Held
The Electricity Act is an exhaustive code on all matters concerning electricity – Under the Electricity Act, all issues dealing with electricity have to be considered by the authorities constituted under the said Act – The State Electricity Commission and the APTEL have ample powers to adjudicate in the matters with regard to electricity – These Tribunals are tribunals consisting of experts having vast experience in the field of electricity – In the present case, the High Court erred in directly entertaining the writ petition when the respondent No.1-the writ petitioner before the High Court had an adequate alternate remedy of approaching the State Electricity Commission – Although, availability of an alternate remedy is not a complete bar in the exercise of the power of judicial review by the High Courts but, recourse to such a remedy would be permissible only if extraordinary and exceptional circumstances are made out – While exercising its power of judicial review, the
Catchwords
Court can step in where a case of manifest unreasonableness or arbitrariness is made out – There was not even an allegation with regard to that effect – In such circumstances, recourse to a petition under Article 226 of the Constitution of India in the availability of efficacious alternate remedy under a statute which is a complete code in itself was not justified. [Paras 93-95] Contract – Award of contract, a commercial transaction – Judicial Scrutiny – Scope:
Held
The award of a contract, whether by a private party or by a public body or the State is essentially a commercial transaction – In arriving at a commercial decision, considerations which are paramount are commercial considerations – State can choose its own method to arrive at a decision – It can fix its own terms of invitation to tender and that is not open to judicial scrutiny – State can enter into negotiations before finally deciding to accept one of the offers made to it – Price need not always be the sole criterion for awarding a contract – State may not accept the offer even though it happens to be the highest or the lowest – However, the State, its corporations, instrumentalities and agencies are bound to adhere to the norms, standards and procedures laid down by them and cannot depart from them arbitrarily – Though that decision is not amenable to judicial review, the court can examine the decision-making process and interfere if it is found vitiated by mala fides, unreasonableness and arbitrariness – Only when the Court comes to a conclusion that overwhelming public interest requires interference, the court should intervene. [Para 102]
Reporter's headnote (continued) and case details
(Civil Appeal No. 6503 of 2022)
Headnotes Electricity Act, 2003 – ss.63, 86 – Rajasthan Rajya Vidyut Prasaran Nigam Limited (RVPN) filed Petition before the State Commission seeking approval for procurement of 1000 MW of power by a competitive bidding process – RFP was issued – Eventually, in consonance with the LoI, PPAs were signed with the L-1, L-2 and L-3 bidders – State Commission held that the quantum of only 500 MW power was liable to be approved considering the demand in the State as recommended by the EAC and it approved the tariff quoted by the L-1 to L-3 bidders – Appeals filed by L-2 and L-3 bidders before APTEL, allowed – Challenged by the appellants – Subsequently, Civil Appeals were filed by L-5 bidder also– Disposing of the appeals, State Commission was directed to go into the issue of approval for adoption of tariff with regard to L-4 and L-5 bidders– Further, * Author
p. 910
p. 911
p. 912
p. 913
p. 914
Digital Supreme Court Reports
AIR 1963 SC 1; Deccan Paper Mills Company Limited v. Regency Mahavir Properties & Ors. [2020] 13 SCR 427 : (2021) 4 SCC 786; Tata Power Company Limited Transmission v. Maharashtra Electricity Regulatory Commission & Ors. [2022] 19 S.C.R. 620 : 2022 SCC Online 1615; Tata Cellular v. Union of India [1994] 2 Suppl. SCR 122 : (1994) 6 SCC 651; Rajasthan Housing Board and another v. G.S. Investments and another [2006] 7 Suppl. SCR 868 : (2007) 1 SCC 477; Laxmikant and others v. Satyawan and others [1996] 3 SCR 532 : (1996) 4 SCC 208; Reliance Infrastructure Limited v. State of Maharashtra and others [2019] 1 SCR 886 : (2019) 3 SCC 352; Radha Krishan Industries v. State of Himachal Pradesh and others [2021] 3 SCR 406 : (2021) 6 SCC 771; South Indian Bank Ltd. and others v. Naveen Mathew Philip and another [2023] 4 SCR 18 : 2023 SCC OnLine SC 435; Air India Ltd. v. Cochin International Airport Ltd. and others [2000] 1 SCR 505 : (2000) 2 SCC 617 – referred to.
List of Acts Electricity Act; RERC (Power Purchase & Procurement Process of Distribution Licensee) Regulations 2004; Constitution of India; General Clauses Act.
List Keywords Electricity; State Electricity Regulatory Commission; Appellate Tribunal for Electricity; Bid Evaluation Committee; Request for Proposal; Power Purchase Agreement; Reduction of quantum of power; Test of filling the bucket; Tariffs not aligned to the prevailing market prices; Consumers’ interest; Competitive Bidding Guidelines/ Process; Approval for adoption of tariff; Determination of tariff by bidding process; Functions of State Commission; Functions of Central Electricity Regulatory Commission; Bid Evaluation Committee; Mandamus; Contract harmful to the public interest; Interpretation of Statutes; Principle of literal interpretation; Principle of purposive construction; Determination of tariff, Regulating tariff; Alternate remedy; Judicial review; Unreasonableness or arbitrariness; Award of contract; Commercial transaction; Commercial considerations; Judicial Scrutiny.
p. 915
CIVIL APPELLATE JURISDICTION : Civil Appeal No. 6503 of 2022. From the Judgment and Order dated 20.09.2021 of the High Court of Judicature for Rajasthan Bench at Jaipur in D.B. Civil Writ Petition No.14815 of 2020. With Civil Appeal Nos. 6502 of 2022 And 4612 of 2023. Appearances for Parties P. Chidambaram, Sr. Adv., Anand K Ganesan, Amal Nair, Ms. Shivani Verma, Nitin Saluja, Nikunj Dayal, Ms. Kritika Khanna, Advs. for the Appellants. Vikramjit Banerjee, A.S.G., Dr. A.M. Singhvi, Prag Tripathi, C.S. Vaidhyanathan, Sr. Advs., Atul Shanker Mathur, Mahesh Agarwal, Rishi Agrawala, Vaibhav Mishra, Dr. Rajeshwar Singh, Avishkar Singhvi, Ms. Priya Singh, Prabal Mehrotra, Shubhankar, Ankur Saigal, Karan Verma, Apoorv Agarwal, E. C. Agrawala, Atul Shankar Mathur, Buddy Rangnathan, Umang Katariya, Ms. Mishika Bajpai, Ms. Apoorva Agrawal, Sidharth Seem, M/s. Khaitan & Co., Jayant Mohan, Zoheb Hossain, P.V. Yogeshwaran, Siddhartha Sinha, Ms. Megha Saxena, Aditya Kashyap, Ms. Vanshja Shukla, Nring C. Zeliang, Gurmeet Singh Makker, Saurabh Mishra, Ms. Prerna Singh, Guntur Prabhakar, Ravi Kishore, Guntur Pramod Kumar, Umesh Kumar Khaitan, Advs. for the Respondents.
- Cases cited
- PTC India Limited v. Central Electricity Regulatory Commission, Through Secretary [2010] 3 SCR 609 : (2010) 4 SCC 603; Vivek Narayan Sharma and others v. Union of India and others [2023] 1 SCR 1 : (2023) 3 SCC 1 – followed. Energy Watchdog v. Central Electricity Regulatory Commission and others [2017] 3 SCR 153 : (2017) 14 SCC 80; GMR Warora Energy Limited v. Central Electricity Regulatory Commission (CERC) & Ors. [2023] 8 SCR 183 : 2023 SCC Online SC 464 – relied on. R.Viswanathan and others v. Rukn-ul-Mulk Syed Abdul Wajid since deceased and others [1963] 3 SCR 22 :
Judgment
Judgment / Order of the Supreme Court Judgment B. R. Gavai, J.
CIVIL APPEAL NO. 6503 OF 2022 AND CIVIL APPEAL NO. 6502 OF 2022
11. These appeals challenge the judgment and order dated 20th September 2021, passed by the Division Bench of the High Court of Judicature for Rajasthan, Bench at Jaipur, in D.B. Civil Writ Petition No. 14815 of 2020, thereby allowing the said writ petition filed by MB Power (Madhya Pradesh) Limited (hereinafter referred to as “MB Power”), respondent No.1 herein. By the impugned judgment and order, the
p. 916
Digital Supreme Court Reports
High Court held that the respondent Nos. 1 to 5 therein (appellants herein and the State of Rajasthan) are bound to purchase a total of 906 MW electricity from the successful bidders. It, therefore, directed the writ petitioner- MB Power (respondent No.1 herein) and respondent No.7 - PTC India Ltd. (hereinafter referred to as “PTC India”) in the said writ petition (respondent No.2 in the present appeals) to supply 200 MW electricity to the respondents therein (appellants herein) within the limit of 906 MW. It also directed the writ petitioner-MB Power and PTC India, respondent No.7 in the said writ petition, to file an appropriate application before the respondent Nos. 1 to 5 in the said writ petition, within two weeks from the date of the order, complying with the necessary requisite conditions, including bank guarantee etc., as required in terms of the Request for Proposal (hereinafter referred to as “the RFP”). It further directed the respondent Nos. 1 to 5 in the said writ petition, for issuance of Letter of Intent (“LoI” for short) in respect of bid filed through PTC India for supplying 200 MW power from the power generating station of the writ petitioner i.e. MB Power at levelized tariff of Rs.5.517/Kwh, being in terms of their bid qualified by the Bid Evaluation Committee (“BEC” for short) and ranked L-7. It further directed the respondents No.1 to 5 in the said writ petition, to immediately within two weeks thereafter, execute the Power Purchase Agreement (“PPA” for short) with PTC India for procuring 200 MW power from the power generating station of MB Power, and then to start procuring power in accordance with law. As an interim measure, it directed that the tariff to be actually paid by the procurer-respondents before it, shall be the interim tariff i.e. Rs.2.88 per unit, as specified by this Court in its interim order dated 28th September 2020, passed in I.A. No.83693 of 2020 in Civil Appeal No.2721 of 2020. It further held that the final adoption of tariff to be paid to PTC India (respondent No.7 before it) under the PPA shall be subject to the final outcome of the said Civil Appeal No. 2721 of 2020, pending before this Court.
BRIEF FACTS:
22. The facts leading to the filing of these two appeals, as mentioned in Civil Appeal No. 6503 of 2022, are as under: 2.1 The Government of India vide Notification dated 19th January 2005, notified the Competitive Bidding Guidelines (hereinafter referred to as “the Bidding Guidelines”) under Section 63 of the
p. 917
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
Electricity Act, 2003 (hereinafter referred to as “the Electricity Act”). The objective of the said Bidding Guidelines is for introduction of competition and protection of consumer interest. 2.2 On 21st September 2009, Rajasthan Rajya Vidyut Prasaran Nigam Limited (hereinafter referred to as “RVPN”) filed Petition No.205 of 2009 before the Rajasthan Electricity Regulatory Commission (hereinafter referred to as “the State Commission”) seeking approval for procurement of 1000 MW of power by a competitive bidding process. 2.3 On 28th May 2012, RVPN issued an RFP, inviting sellers to participate in the competitive bidding for procurement of 1000 MW under the Bidding Guidelines. 2.4 In the month of February 2013, bids were received from the bidders. 2.5 On 4th April 2013, based on the preliminary evaluation of the non-financial bids by the BEC, 7 bidders were declared as qualified for opening of the financial bids. The respondent No.1-MB Power herein was not a bidder in the above process. Respondent No.2-PTC India herein had submitted a bid for 1041 MW, which it was to procure from five different generators. PTC India is a power-trading licensee company, which had procured the bid document after depositing a Bid Bond. 2.6 In the various meetings held between 17th April 2013 and 22nd April 2013, the BEC had placed the bids received in ascending order, from lowest to the highest tariff as follows:
Rank Qualified Levelized Tariff Capacity Cumulative Average Bidder Name (Rs/kWh) Offered Capacity Cumulative Offered Tariff (Rs/ kWh) L-1 PTC – Maruti 4.517 195 195 4.517 Clean Coal and Power Limited L-2 PTC – DB 4.811 311 506 4.698 Power Limited
p. 918
Digital Supreme Court Reports
L-3 LPL – Lanco 4.943 100 606 4.738 Babandh Power Limited L-4 PTC – Athena 5.143 200 806 4.839 Chhattisgarh Power Ltd L-5 SKS Power 5.300 100 906 4.890 Generation (Chhattisgarh) Limited L-6 LPL – Lanco 5.490 100 1006 4.949 Vidarbha Thermal Power Limited L-7 PTC – MB 5.517 200 1206 5.043 Power (Madhya Pradesh) Ltd. L-8 KSK 5.572 475 1681 5.193 Mahanadi Power Company Limited L-9 Jindal Power 6.038 300 1981 5.321 Limited L-10 LPL – Lanco 7.110 100 2081 5.407 Amarkantak Power Ltd
2.7 In the 216th Meeting of the Board of Directors of RVPN, it was decided to take an opinion from the BEC as to whether negotiations should be held to reduce tariff keeping in view of the long-term impact and quantum of the amounts involved. 2.8 On 4th June 2013, the BEC gave its opinion that since the rates quoted vary considerably, negotiations could be held with the bidders. 2.9 Vide Resolution dated 4th June 2013, the Board of the RVPN decided to hold negotiations with the qualified bidders. 2.10 In the negotiations, the following offers were received:
p. 919
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
Footnotes
“S. Bidder Quoted Capacity Additional No. Tariff offered in Capacity (Rs. / Bid (MW) Offered kWh) (MW) 1 M/s PTC India Ltd 4.517 195 55 (through developer M/s Maruti Clean Coal and Power Limited) 2 M/s PTC India Ltd (through 4.811 311 99 their developer M/s DB Power Limited)4.811 3 M/s Lanco Power Limited 4.892 100 250 (Generation Source – M/s Lanco Babandh Power Limited) Total 606 404 G. Total (A+B) 1010 MW” 2.12 In consonance with the LoI, on 1st November 2013, PPAs were signed with the L-1, L-2 and L-3 bidders. Thereafter, RVPN filed Petition No.431 of 2013 before the State Commission under Section 63 of the Electricity Act read with clause 5.16
p. 920
Digital Supreme Court Reports
of the Bidding Guidelines for adoption of tariff for purchase of long-term base load power of 1000 MW (±10%) as quoted by the successful bidders (being L-1, L-2 and L-3) under the Case-I bidding process. 2.13 The Energy Assessment Committee (“EAC” for short), constituted by the Government of Rajasthan pursuant to Regulation 3 of the Power Procurement Regulations, in its 4th meeting held on 29th January 2014, recommended that there was no requirement for long term procurement of 1000 MW (±10%) power under Case-I for which PPAs had been executed and tariff adoption petition had been filed before the State Commission. 2.14 In the meantime, the L-4 and L-5 bidders filed Writ Petitions being CWP No. 19437 of 2013 and CWP No.18699 of 2013 respectively, before the High Court, seeking to strike down the negotiations process and the higher quantum awarded to L-1, L-2 and L-3 bidders. 2.15 The High Court vide judgment dated 7th February 2014, refused to entertain the writ petitions and relegated the parties to the State Commission. The said order dated 7th February 2014 came to be challenged by the L-4 and L-5 bidders by way of writ appeals being DB Special Appeals (Writ) Nos. 538 of 2014 and 604 of 2014. The said appeals also came to be dismissed by the High Court vide judgment and order dated 18th April 2014. 2.16 Subsequently, in its 5th meeting held on 21st May 2014, the EAC recommended that as against the quantum of 1000 MW power, for which PPAs had been executed and tariff adoption petition had been filed, a demand of 600 MW power ought to be considered, on account of availability of power from various sources and to meet future contingencies. 2.17 The Government of Rajasthan, therefore, vide its letter dated 25th July 2014, issued to the RVPN, approved the purchase of a quantum of 500 MW power on long term basis as against the quantum of 1000 MW for which PPAs had already been executed.
p. 921
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
2.18 On the basis of the decision/recommendation of the EAC and the direction issued by the Government of Rajasthan, RVPN filed an application under Regulation 7 of the RERC (Power Purchase & Procurement Process of Distribution Licensee) Regulations 2004 (hereinafter referred to as “RERC Regulations 2004”) in Petition No.431 of 2013, to bring on record the EAC decision/recommendation and the Government of Rajasthan approval. In the said application, inter alia, it was prayed for adoption of tariff and approval of the reduced quantum of 500 MW of power to be purchased as against the original 1000 MW of power for which PPAs had already been executed with the successful bidders. 2.19 Vide order dated 22nd July 2015 in Petition No.431 of 2013, the State Commission held that the quantum of only 500 MW power was liable to be approved considering the demand in the State as recommended by the EAC. The State Commission also approved the tariff quoted by the L-1 to L-3 bidders. 2.20 Aggrieved by the reduction of quantum by the State Commission, the L-2 and L-3 bidders preferred appeals before the learned Appellate Tribunal for Electricity (hereinafter referred to as “the learned APTEL”) being Appeal Nos. 235 of 2015 and 191 of 2015 respectively. 2.21 Two separate appeals were also preferred by the L-4 and L-5 bidders, being Appeal No. 264 of 2015 and Appeal No. 202 of 2015 respectively, wherein apart from challenging the reduction of quantum by the State Commission from 1000 MW to 500 MW, the increase in quantum granted to the L-1, L-2 and L-3 bidders was also challenged. 2.22 Vide order dated 2nd February 2018, the learned APTEL allowed the Appeal Nos. 191 of 2015 and 235 of 2015, filed by the L-3 and L-2 bidders, holding that the reduction of quantum by the State Commission from 1000 MW to 500 MW was incorrect. It, therefore, directed the State Commission to pass consequential orders for approving the PPAs for the L-2 and L-3 bidders for the higher quantum which was negotiated. 2.23 The order of the learned APTEL dated 2nd February 2018, was challenged by the present appellants before this Court by
p. 922
Digital Supreme Court Reports
way of Civil Appeal Nos. 3481-3482 of 2018, on the ground that the RFP quantum cannot be restored from 500 MW to 1000 MW. Subsequently, Civil Appeal Nos. 2502-2503 of 2018 also came to be filed by L-5 bidder- SKS Power Generation (Chhattisgarh) Limited (hereinafter referred to as “SKS Power”), on the ground that the State Commission could not have permitted the procurement of higher quantum by the L-2 and L-3 bidders. 2.24 Vide order dated 25th April 2018, the said Civil Appeals were disposed of by this Court, upholding the decision of the learned APTEL, setting aside the reduction of quantum of procurement from 1000 MW to 500 MW after the bidding process was over. However, this Court held that the decision of the learned APTEL on the quantum to be procured from individual bidders was liable to be reversed and that the quantum originally offered by the bidders in the bidding process has to be taken into consideration and increase in quantum by means of negotiation was not permissible. Insofar as L-4 and L-5 bidders are concerned, since the tariff quoted was not considered at any stage by either the procurer, or by RVPN or by the State Commission, this Court directed the State Commission to go into the issue of approval for adoption of tariff with regard to L-4 and L-5 bidders. 2.25 Subsequent to the judgment and order dated 25th April 2018, passed by this Court, the BEC came to a finding that the tariffs quoted by the L-4 and L-5 bidders were not aligned to the prevailing market prices. 2.26 In the meantime, vide order dated 19th November 2018, this Court, on an application filed by RVPN, directed the State Commission to go into the issue of adoption of tariff in terms of Section 63 of the Electricity Act and the law laid down by this Court under the said provision. 2.27 Vide order dated 26th February 2019, the State Commission held that the tariffs offered by the L-4 and L-5 bidders were not aligned to the prevailing market prices. 2.28 Being aggrieved by the same, SKS Power (L-5 bidder) challenged the above order dated 26th February 2019 before the learned APTEL by way of Appeal No.224 of 2019.
p. 923
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
2.29 Vide the judgment and order dated 3rd February 2020, the learned APTEL allowed the appeal of the L-5 bidder – SKS Power and held that the State Commission had to necessarily adopt the tariff, and had no power to consider whether the tariff was aligned to market prices. 2.30 Aggrieved by the same, the present appellants have filed Civil Appeal No. 1937 of 2020 and Civil Appeal No.2721 of 2020. Initially, the present appeals were tagged along with the said appeals. However, vide order dated 10th October 2023, the same have been de-tagged. 2.31 On an interlocutory application being I.A. No.83693 of 2020 filed by L-5 bidder-SKS Power in Civil Appeal No. 2721 of 2020, an interim order 28th September 2020, came to be passed by this Court, holding that the L-5 bidder was entitled to supply power to the appellants at the tariff of Rs.2.88 per unit. 2.32 It appears that subsequently thereafter on 14th December 2020, a writ petition being Writ Petition No. 14815 of 2020 came to be filed by the respondent No.1-MB Power before the High Court, seeking following relief: “(a) Issue appropriate Writ or order or direction in the nature of declaration or certiorari or any other writ or direction declaring Rule 69(2)(b) of the RTPP Rules as ultra vires Article 14, 19(1)(g) and 21 of the Constitution of India as well as Section 63 of the Electricity Act, 2003; (b) Issue appropriate Writ or order or direction in the nature of mandamus directing the Respondent Nos. 1-4 to immediately issue a Letter of Intent in favour of the Petitioner, sign the power Purchase Agreement with the Petitioner as per its bid tariff, take steps for adoption of tariff of the Petitioner and immediately commence supply of power; (c) Pass such further order(s) as this Hon’ble Court may deem fit and proper in the facts and circumstances of the instant case in the interest of justice.”
p. 924
Digital Supreme Court Reports
2.33 In the appeals filed by the present appellants, i.e., Civil Appeal Nos. 1937 of 2020 and 2721 of 2020, respondent No.1-MB Power filed an application for impleadment, on the ground that the issue of role of the State Commission in adoption of tariff being decided by this Court in the said appeals would have an impact on the writ petition filed by it before the High Court. 2.34 Vide order dated 19th April 2021, this Court directed the said application for impleadment to be considered at the stage of hearing of the said appeals. 2.35 By the impugned judgment and order, the said writ petition filed by MB Power has been allowed by the High Court in terms of the aforesaid directions. 2.36 Hence the present appeals.
CIVIL APPEAL NO. 4612 OF 2023
33. This appeal filed by Rajasthan Urja Vikas Nigam Limited (hereinafter referred to as “RUVNL”) challenges the order dated 1st June 2023, passed by the learned APTEL, whereby the learned APTEL has stayed the operation of the order dated 31st March 2023, passed by the State Commission in Petition No.RERC-2097 of 2023.
44. The facts, in brief, leading to the filing of Civil Appeal No.4612 of 2023, are as under: 4.1 In the year 2022, the RUVNL had proposed the procurement of 294 MW of power on long term basis and for that purpose had filed Petition No.2017 of 2022 before the State Commission. 4.2 Vide order dated 2nd November 2022, the State Commission rejected the procurement of power on long term basis. 4.3 Thereafter, considering the assessment and requirement of power, the RUVNL filed Petition No.RERC-2097 of 2023 before the State Commission, seeking approval for procurement of 160 MW of power on medium term basis i.e., for a period of 5 years and not for 25 years on long term basis.
p. 925
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
4.4 Vide order dated 31st March 2023, the State Commission granted approval to the distribution licensees in the State of Rajasthan for procurement of 160 MW round-the-clock fuel agnostic power on medium term basis by way of a competitive bidding process. 4.5 Aggrieved thereby, the respondent No.1 herein, i.e., MB Power (Madhya Pradesh) Limited filed Appeal No. 466 of 2023 before the learned APTEL against the order dated 31st March 2023 passed by the State Commission, along with I.A. No.1004 of 2023 for the stay of the order. 4.6 Vide impugned order dated 1st June 2023, the learned APTEL stayed operation of the order passed by the State Commission and directed that in the bidding process for procurement of 160 MW of power on medium term basis the bid shall neither be finalized nor shall any Letter of Intent be issued pursuant to the opening of the bids. 4.7 Aggrieved thereby, the RUVNL has filed the present appeal.
55. Vide order dated 26th September 2023, this Court had permitted the appellant to proceed further with the tender process for procurement of 160 MW of power for 5 years on the basis of model bidding documents for medium term procurement.
66. Vide order dated 10th October 2023, this Court had been informed that pursuant to the aforesaid order dated 26th September 2023, bids had been opened and the lowest bid was at Rs.5.30 per unit. As a result, this Court had clarified that the pendency of the present appeal would not come in the way of the appellant in finalizing the tender and executing power purchase agreement with the successful bidders and the appellant would be at liberty to do so in order to overcome the difficulty of power shortage.
77. The order of the learned APTEL dated 1st June 2023 basically relies on the judgment of the Division Bench of the High Court of Judicature for Rajasthan, bench at Jaipur, passed in D.B. Civil Writ Petition No. 14815 of 2020, which is a subject matter of challenge in Civil Appeal Nos. 6503 of 2022 and 6502 of 2022. As such, the result of Civil Appeal No.4612 of 2023 would depend upon the outcome of Civil Appeal Nos. 6503 of 2022 and 6502 of 2022.
p. 926
Digital Supreme Court Reports
SUBMISSIONS OF THE APPELLANTS
88. We have heard Shri P. Chidambaram, learned Senior Counsel appearing for the appellants, and Dr. A.M. Singhvi and Shri C.S. Vaidyanathan, learned Senior Counsel appearing for the respondents.
99. Shri Chidambaram, at the outset, submits that the writ petition, filed by the respondent No.1-MB Power, was not maintainable before the High Court in its original jurisdiction under Article 226 of the Constitution of India. It is submitted that, if the respondent No.1-MB Power had any grievance, it could have either approached the State Commission or the learned APTEL.
1010. He submits that this Court in the case of PTC India Limited v. Central Electricity Regulatory Commission, Through Secretary1 has held that the Electricity Act is an exhaustive code on all matters concerning electricity. The Electricity Act provides for the forum for adjudication of all disputes between a generator and the procurer/licensee. As such, the respondent No.1-MB Power, if had any grievance, ought to have filed an application before the State Commission or the learned APTEL and it could not have approached the High Court directly in its writ jurisdiction.
1111. Shri Chidambaram further submitted that though L-1 to L-5 bidders have continuously been litigating their grievances from 2013 onwards, the respondent No.1-MB Power, since it was not short- listed, had taken no steps from 2013 onwards. It is submitted that, as a matter of fact, the bid of L-7 bidder was returned and on 6th January 2015, the Bid Bond bank guarantee was also directed to be not extended. Still, it kept silent for about 6 years. He further submits that even after the judgment and order was passed by this Court on 25th April 2018, respondent No.1-MB Power did not take any steps for about two years, and for the first time, on 14th December 2020, it filed a writ petition before the High Court. As such, it is clear that the respondent No.1-MB Power had acquiesced the direction by the appellants dated 6th January 2015 not to renew the Bid Bond bank guarantee. Shri Chidambaram, therefore, submits that the writ petition was liable to be dismissed on the ground of delay and laches itself.
Footnotes
p. 927
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
1212. Shri Chidambaram further submits that the term “successful bidder” has been defined in the RFP. It is submitted that the bidder(s) selected by the procurer/authorized representative, pursuant to the RFP for supply of power by itself or through the project company as per the terms of the RFP, and to whom a LoI has been issued, can only be termed as the “successful bidder”. Since no LoI was issued to the respondent No.1-MB Power, it could not be construed as a “successful bidder”.
1313. Shri Chidambaram submits that the theory of “filling the bucket”, as put forth by the respondent No.1-MB Power, has no basis either in the RFP or in the Bidding Guidelines. It is further submitted that the said theory is a dangerous proposition inasmuch as, it is expected that the procurer would be obliged to accept the bids of lower ranked financial bids, irrespective of the exorbitant tariff quoted by them. Shri Chidambaram has given an illustration to that effect that, if in a bid to procure 1000 MW, 2 bidders can be put forward as stalking horses who would bid lower tariffs and are ranked as L-1 and L-2. Thereafter, L-3 onwards can quote exorbitant tariffs which are not aligned to market prices. He submits that this specious theory of “filling the bucket”, which would oblige the procurer to go to the last bidder, irrespective of their tariffs being completely exorbitant, is very dangerous. It is submitted that, in any case, clause 3.5.12 of the RFP enables the procurer to reject any bid where the quoted tariff is not aligned to market prices.
1414. Shri Chidambaram further submits that the directions issued by this Court vide order dated 25th April 2018, were specifically restricted to L-1 to L-5 bidders, which were litigating. It is submitted that the contention of the respondent No.1-MB Power that the order of this Court dated 25th April 2018 was an order in rem is erroneous.
1515. Relying on the judgment of this Court in the case of R. Viswanathan and others v. Rukn-ul-Mulk Syed Abdul Wajid since deceased and others2, Shri Chidambaram submits that the judgment in rem settles the destiny of the res itself. Whereas an order in personam determines the rights of persons before the Court and binds only
Footnotes
p. 928
Digital Supreme Court Reports
the parties to the lis. Reliance in this respect is also placed on the judgment of this Court in the case of Deccan Paper Mills Company Limited v. Regency Mahavir Properties & Ors.3
1616. Shri Chidambaram further submits that the reliance by the respondents on the certificate, which certified the bid evaluation process was carried out in conformity with the provisions of the RFP, and, therefore, it is not permissible to go into the determination of tariff is incorrect. He submits that the certificate is not certifying that L-7 was qualified to be selected as a “successful bidder” or it had earned a right to have his bid accepted irrespective of the quoted tariff. He submits that if the quoted tariff of L-4 bidder of Rs.5.143 and L-5 bidder of Rs.5.300 were misaligned, then, most certainly, the quoted tariff of L-7 bidder of Rs.5.517 was also misaligned.
1717. The learned Senior Counsel submits that the jurisdiction under Section 63 of the Electricity Act is not that of a mere post office. The State Commission has a power to reject the adoption of tariff if it is not aligned to market prices. In this respect, he refers to the judgments of this Court in the cases of Tata Power Company Limited Transmission v. Maharashtra Electricity Regulatory Commission & Ors.4 and Energy Watchdog v. Central Electricity Regulatory Commission and others5.
1818. Shri Chidambaram submits that the State Commission while adopting the tariff is bound to take into consideration the protection of consumer interest. Reliance in this respect has been placed on the judgment of this Court in the case of GMR Warora Energy Limited v. Central Electricity Regulatory Commission (CERC) & Ors.6, wherein this Court has emphasized the need for balancing the interest of the consumers with that of the generators.
1919. Shri Chidambaram further submits that in view of clauses 2.15.1 and 3.5.12 of the RFP and clause 5.15 of the Bidding Guidelines, the appellants had the power to reject all price bids if the rates quoted are not aligned to the prevailing market prices.
3 [2021] 13 SCR 786 : (2021) 4 SCC 786=2020 INSC 497 4 [2022] 19 SCR 620 : 2022 SCC Online 1615=2022 INSC 1220 5 [2017] 3 SCR 153 : (2017) 14 SCC 80=2017 INSC 338 6 [2023] 8 SCR 183 : 2023 SCC Online SC 464=2023 INSC 398
p. 929
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
2020. Shri Chidambaram lastly submitted that the bidders have no vested right to contract. Article 226 of the Constitution of India cannot be used to award a contract in favour of the bidder. In this respect, he refers to the following judgments of this Court: i. Tata Cellular v. Union of India7 ii. Rajasthan Housing Board and another v. G.S. Investments and another8 iii. Laxmikant and others v. Satyawan and others9
2121. Shri Chidambaram, therefore, submits that the impugned judgment and order is not sustainable and is liable to be set aside.
SUBMISSIONS OF THE RESPONDENTS
2222. Dr. A.M. Singhvi, learned Senior Counsel, per contra, submits that unlike Section 62 read with Sections 61 and 64 of the Electricity Act, under Section 63 of the Electricity Act, the appropriate Commission only “adopts” tariff and does not “determine” tariff. However, in cases under Section 63 of the Electricity Act, the Central Commission is bound by the guidelines issued by the Central Government and it is required to exercise its regulatory functions, albeit under Section 79(1)(b) only in accordance with those guidelines. In this respect, he relies on the judgment of this Court in the case of Energy Watchdog (supra) and Tata Power Company Limited Transmission (supra).
2323. Dr. Singhvi submits that two issues that can be considered in a case under Section 63 of the Electricity Act by the Commission are: (1) as to whether the bidding process was transparent; and (2) as to whether the bidding process was held in accordance with the guidelines issued by the Central Government.
2424. He submits that once the tariff is an outcome of the bidding process and the bidding process is transparent and held in accordance with the Bidding Guidelines, the appropriate Commission is mandated to adopt such tariff and it does not have a discretion to go into the question as to whether it is market aligned or not.
7 [1994] 2 Supp. SCR 122 : (1994) 6 SCC 651 (para 94)= 1994 INSC 283 8 [2006] 7 Supp. SCR 868 : (2007) 1 SCC 477 (para 8, 9 and 11)= 2006 INSC 766 9 [1996] 3 SCR 532 : (1996) 4 SCC 208=1996 INSC 409
p. 930
Digital Supreme Court Reports
2525. Dr. Singhvi further submits that while adopting an already determined tariff by the bidding process as per Section 63 of the Electricity Act, the issue of market alignment of respondent No.1’s bid does not and cannot arise for consideration in these proceedings.
2626. Without prejudice to the aforesaid submissions, Dr. Singhvi submits that it is not permissible for the State Commission to go into the question of market alignment. He submitted that the respondent No.1’s quoted tariff was market aligned not only in the year 2013 but also today. Dr. Singhvi submits that in the recent tender for procurement of 160 MW electricity, conducted in pursuance to the permission granted by this Court, the lowest bid for 1st year tariff discovered and approved by the appellants is at Rs.5.30 per unit. It is submitted that there is a vast difference between “1st year tariff” and “levelized tariff”. Dr. Singhvi submits that however, if this offer for supply in the first year of the bid is to be levelized for 25 years, it would come to Rs.7.91 per unit, which is around 50% higher than the 1st year tariff of the said bidder itself.
2727. Dr. Singhvi submits that M/s Deloitte is a common consultant insofar as the appellants and the Uttar Pradesh Power Corporation Limited (“UPPCL” for short). He submits that, in fact, BEC of UPPCL, in March 2013, accepted tariff up to Rs. 5.849 per unit i.e., a tariff much higher than that of respondent No.1-MB Power. It is submitted that the bidding period in the present case as well as in the case of UPPCL is the same. It is submitted that, however, in 2018, the Rajasthan BEC mischievously and selectively considered tariff only up to 2012 and compared bids of Andhra Pradesh and Kerala, which were, in fact, discovered in 2015 and 2014 respectively. It is submitted that similarly, in the State of Tamil Nadu, for the same period, the equivalent levelized tariff was determined by M/s Deloitte at Rs.5.75 per unit for 25 years and the same was accepted. It is, therefore, submitted that, considering the aforesaid, the levelized tariff of the respondent No.1-MB Power for 25 years at Rs.5.517 per unit is indisputably market aligned even as on 2012-2013.
2828. Dr. Singhvi, relied on the following charts to show that the levelized tariff for 25 years, as quoted by the respondent No.1-MB Power, is very much market aligned.
p. 931
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
“Market Price as of 2012-13 – at the time of Rajasthan Bid
Procurer State 1st Year Levelized PPA Duration Quoted Tariff for 25 Tariff years
Rajasthan – L5 (i.e. 3.976 5.300 25 years SKS)
Rajasthan – L7 4.137 5.517 25 years (i.e. R1 – MB Power Bid)
UP – 2013 Tariff 4.36 5.849 25 years approved by BEC (Deloitte as consultant)
TN – Approved 4.117 5.75 15 years Tariff
Prices discovered in Rajasthan Medium Term Tender in Sept / Oct 2023
Procurer State 1st Year Levelized PPA Quoted Tariff for 25 Duration Tariff years Rajasthan – 2023 5.30 7.91 5 years Rajasthan – R1 (i.e. L7 – 4.137 5.517 25 years” MB Power 2012 Bid)
2929. Dr. Singhvi, the learned Senior Counsel, relying on clause 3.5.9 of the RFP, submits that, no negotiations were permissible in spite of the specific clause in the RFP and the opinion to the contrary given by the consultant. It is submitted that the appellants tried to negotiate the prices with L-1 to L-3 bidders, which decision has been finally set aside by this Court vide order dated 25th April 2018.
p. 932
Digital Supreme Court Reports
3030. Dr. Singhvi submits that in view of the specific certificate dated 4th June 2013, issued by the BEC, certifying that the bidding procedure for the bids in question had been carried out by the appellants in conformity with the provisions of the RFP and the Bidding Guidelines issued by the Government of India, it is not permissible for the appellants to take a contradictory stand.
3131. Dr. Singhvi submits that what this Court had directed by order dated 25th April 2018, was to adopt the tariff with regard to L-4 and L-5 bidders. By the subsequent order dated 19th November 2018, this Court clarified and directed to decide the tariff under Section 63 of the Electricity Act having regard to the law laid down both statutorily and by this Court. It is submitted that the only scrutiny that could be done by the Commission was only with regard to the following of the twin requirements as observed by this Court in the case of Energy Watchdog (supra).
3232. Dr. Singhvi submits that the power to reject the bids is in respect of all price bids. He submits that if it is found that the bidding process was not transparent and the Guidelines were not followed or the bids are not market aligned, then the appellants would be entitled to reject all bids and not individually and selectively some bids. He submits that if the interpretation as placed by the appellants is to be accepted, it will vest an arbitrary power with the procurer of energy to arbitrarily reject the bid of any of the bidders. It is submitted that such an unfettered and unchecked discretion cannot be permitted to be exercised by the appellants/distribution companies (“DISCOMS”).
3333. Dr. Singhvi submits that insofar as the aspect with regard to “consumer’s interest” is concerned, the learned APTEL has squarely covered the same. It has been held by the learned APTEL that the consumers’ interest is a broad term and among others, involves reliable, quality and un-interrupted power on long term basis besides being competitive.
3434. The learned Senior Counsel submits that the State of Rajasthan needed 1000 MW of power when it invited the bids in question. He submits that the DISCOMS have even fairly admitted that they are still in need of power and as such, filed an Interlocutory Application
p. 933
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
being I.A. No. 150366 of 2023 in Civil Appeal No.4612 of 2023 (for permission to file additional documents) seeking permission to procure power for medium term from the State Commission. It is, therefore, submitted that even in the larger public interest and consumer interest, the appellants should procure the power from the respondent No.1-MB Power. Dr. Singhvi submits that the appellants are bound to procure 906 MW of power in view of the orders passed by this Court on 25th of April 2018. He submits that the RFP provides for bucket filling. It is, therefore, submitted that the appellants are required to procure the power going down the ladder from the bidders starting from L-1 to the one till procurement of 906 MW of power is complete. It is submitted that since many of the bidders had now gone into insolvency, it is only 3 bidders, which are left in the fray. L-1 bidder is supplying 195 MW power and L-2 is supplying 311 MW power. It is submitted that even in the event, this Court permits L-5 bidder to supply 100 MW power and 160 MW power for medium term in pursuance to the order passed by this Court on 26th September 2023, still the total would not be beyond 766 MW. Still the balance of 140 MW power would remain.
3535. Dr. Singhvi submits insofar as contention of the appellants with regard to delay and laches is concerned, the same is without substance. He submits that only after the respondent No.1 came to know about the incapacity of L-3, L-4 and L-6 bidders to honour their offered capacity, the occasion to revalidate the claim of the respondent No.1 arose. The learned Senior Counsel, relying on clause 3.5.6 of the RFP, submits that the selection process shall continue till the requisitioned capacity has been achieved through the summation of the quantum offered by the “successful bidders” or when the balance of the requisitioned capacity is less than the minimum bid capacity. It is submitted that since there is still a gap of 140 MW, to comply with this Court’s order dated 25th April 2018, the appellants are bound to enter into PPAs with the qualified bidders until the entire requisitioned capacity of 906 MW is met.
3636. Dr. Singhvi relied on the following chart to show that the prices discovered in all medium and long term bids are much higher than the levelized price quoted by the respondent No.1-MB Power.
p. 934
Digital Supreme Court Reports
“Prices discovered in all medium and long term bids since 2022
Procurer State 1st Year Levelized PPA Duration Quoted Tariff for 25 Tariff years Adani Mumbai– 2022 5.98 8.78 2.1 years Uttarakhand–2023 5.41 7.93 1.5 years Noida Power – 2022 5.15 7.46 3 years Mundra SEZ– 2023 5.00 6.69 15 years Haryana – 2022 5.70 to 5.75 8.36 3 years J & K – 2023 6.05 8.22 5 years Haryana – 2023 6.05 8.22 5 years NDMC – 2023 6.05 8.22 5 years Madhya Pradesh–2023 6.05 8.22 5 years Haryana – 2023 5.79 8.49 5 years Gujarat – 2023 5.18 to 5.69 6.81 15 years Uttarakhand–2023 7.97 11.72 3.5 years Noida Power – 2023 6.30 9.18 3 years”
3737. Dr. Singhvi, therefore, submits that, if the directions as issued by the High Court are maintained, it will be in the interests of the consumers, who will be getting the electricity at lesser prices than what has recently been emerged as a levelized price in the bidding process. He submits that this is specifically so when indisputably even according to the appellants they are in dire need of power. Dr. Singhvi, therefore, prays for dismissal of the present appeals.
3838. Shri C.S. Vaidyanathan, learned Senior Counsel also addressed similar arguments and prayed for dismissal of the present appeals.
CONSIDERATIONS
3939. For considering the rival submissions, it will be necessary to refer to some of the provisions of the Electricity Act, which are as under: “63. Determination of tariff by bidding process. - Notwithstanding anything contained in section 62, the Appropriate Commission shall adopt the tariff if such
p. 935
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
tariff has been determined through transparent process of bidding in accordance with the guidelines issued by the Central Government.” xxx xxx xxx
79. Functions of Central Commission.-(1) The Central Commission shall discharge the following functions, namely:- (a) ……………………………………… (b) to regulate the tariff of generating companies other than those owned or controlled by the Central Government specified in clause (a), if such generating companies enter into or otherwise have a composite scheme for generation and sale of electricity in more than one State; xxx xxx xxx “86. Functions of State Commission.- (1) The State Commission shall discharge the following functions, namely: - (a) ……………. (b) regulate electricity purchase and procurement process of distribution licensees including the price at which electricity shall be procured from the generating companies or licensees or from other sources through agreements for purchase of power for distribution and supply within the State;”
4040. It will also be relevant to refer to part of the preamble of the Bidding Guidelines notified by the Union of India vide Resolution dated 19th January 2005, which is as under: “These guidelines have been framed under the above provisions of section 63 of the Act. The specific objectives of these guidelines are as follows:
1. Promote competitive procurement of electricity by distribution licensees;
p. 936
Digital Supreme Court Reports
2. Facilitate transparency and fairness in procurement processes;
3. Facilitate reduction of information asymmetries for various bidders;
4. Protect consumer interests by facilitating competitive conditions in procurement of electricity;
5. Enhance standardization and reduce ambiguity and hence time for materialization of projects;
6. Provide flexibility to suppliers on internal operations while ensuring certainty on availability of power and tariffs for buyers.”
4141. It will also be relevant to refer to certain clauses of the RFP, which are as under: 2.15 Right to withdraw the RFP and to reject any Bid. 2.15.1 This RFP may be withdrawn or cancelled by the Procurer/ Authorized Representative at any time without assigning any reasons thereof. The Procurer/ Authorized Representative further reserves the right, at its complete discretion, to reject any or all of the Bids without assigning any reasons whatsoever and without incurring any liability on any account.” xxx xxx xxx “3.5 STEP IV- Successful Bidder(s) Selection 3.5.1 Bids qualifying in Step III shall only be evaluated in this stage. 3.5.2 The Levelized Tariff calculated as per Clause 3.4.8 for all Financial Bids of Qualified Bidders shall be ranked from the lowest to the highest. 3.5.3 The Bidder with the lowest Levelized Tariff shall be declared as the Successful Bidder for the quantum of power (in MW) offered by such Bidder in its Financial Bid. 3.5.4 The selection process of the Successful Bidder as mentioned above in Clause 3.5.3 shall be repeated for
p. 937
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
all the remaining Financial Bids of Qualified Bidders until the entire Requisitioned Capacity is met or until the time when the balance of the Requisitioned Capacity is less than the Minimum Bid Capacity. 3.5.5 At any step in the process in Clause 3.5.4, in case the Requisitioned Capacity has not been achieved and the offered capacity of the Bidder with the lowest Levelized Tariff amongst the remaining Financial Bids is larger than the balance Requisitioned Capacity, any fraction or combination of fractions offered by such Bidder shall be considered for selection, towards meeting the Requisitioned Capacity. 3.5.6 The selection process shall stand completed once the Requisitioned Capacity has been achieved through the summation of the quantum offered by the Successful Bidders or when the balance of the Requisitioned Capacity is less than the Minimum Bid Capacity. Provided however in case only one Bidder remains at any step of the selection process and the balance Requisitioned Capacity exceeds the Minimum Bid Capacity, Financial Bid(s) of such Bidder shall be referred to Appropriate Commission and the selection of the Bidder shall then be at the sole discretion of the Appropriate Commission. 3.5.7 At any step during the selection of Successful Bidder(s) in accordance with Clauses 3.5.2 to 3.5.6, the Procurer / Authorized Representative reserves the right to increase / decrease the Requisitioned Capacity by up to ten percent (10%) of the quantum indicated in Clause 1.3.1 to achieve the balance Requisitioned Capacity and select the Successful Bidder with the lowest Levelized Tariff amongst the remaining Bids. Any increase / decrease in the Requisitioned Capacity exceeding ten percent (10%) of the quantum in Clause 1.3.1. can be made only with the approval of the Appropriate Commission.
p. 938
Digital Supreme Court Reports
3.5.8 The Letter(s) of Intent shall be issued to all such Successful Bidder(s) selected as per the provisions of this Clause 3.5. 3.5.9 There shall be no negotiation on the Quoted Tariff between the Authorized Representative/ Procurer and the Bidder(s) during the process of evaluation. 3.5.10 Each Successful Bidder shall unconditionally accept the LOI, and record on one (1) copy of the LOI, “Accepted Unconditionally”, under the signature of the authorized signatory of the Successful Bidder and return such copy to the Procurer/ Authorized Representative within seven (7) days of issue of LOI. 3.5.11 If the Successful Bidder, to whom the Letter of Intent has been issued does not fulfill any of the conditions specified in Clauses 2.2.8 and 2.2.9, the Procurer / Authorized Representative reserves the right to annul the award of the Letter of Intent of such Successful Bidder. Further, in such a case, the provisions of Clause 2.5 (b) shall apply. 3.5.12 The Procurer / Authorized Representative, in its own discretion, has the right to reject all Bids if the Quoted Tariff are not aligned to the prevailing market prices.”
4242. It will also be relevant to refer to clause 5.15 of the Bidding Guidelines, which is as under: “5.1 The bidder who has quoted lowest levellised tariff as per evaluation procedure, shall be considered for the award. The evaluation committee shall have the right to reject all price bids if the rates quoted are not aligned to the prevailing market prices.” [emphasis supplied]
4343. Successful bidder has been defined in the RFP as under: “Successful Bidder(s)” shall mean the Bidder(s) selected by the Procurer/ Authorized Representative, as applicable pursuant to this RFP for supply of power by itself or through the Project Company as per the terms of
p. 939
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
the RFP Documents, and to whom a Letter of Intent has been issued;”
4444. The impugned judgment of the High Court is basically based on the judgment of the learned APTEL dated 3rd February 2020 in the case of SKS Power and orders passed by this Court as already observed herein above. After the bids were received for procurement of 1000 MW, the BEC decided to accept the bids of L-1, L-2 and L-3 bidders. However, as the State government had recommended reduction of purchase to only 500 MW power, RVPN filed an application under Regulation 7 of the RERC Regulations 2004, for adoption of tariff of L-1 to L-3, so also allowing it to purchase only 500 MW of power as against 1000 MW. The said application was allowed by the State Commission. The State Commission also adopted the tariff determined through the bidding process for purchase of 500 MW power vide its order dated 22nd July 2015. The said order of the State Commission was challenged before the learned APTEL by M/s D.B. Power Ltd [L-2 bidder] and by M/s Lanco Power Ltd. [L-3 bidder] by way of Appeal Nos. 235 of 2015 and 191 of 2015 respectively.
4545. The learned APTEL in the said appeals, vide judgment and order dated 2nd February 2018, set aside the order of the State Commission dated 22nd July, 2015, and passed the following directions: “ORDER Hence, the Appeal Nos. 235 of 2015 and 191 of 2015 are allowed and the State Commission’s order dated 22.07.2015 is set aside. The State Commission is directed to pass consequential order in accordance with the law keeping in view our observations made above as well as the judgments of this Tribunal rendered earlier on the aspects of the scope of Section 63 of the Act as expeditiously as possible, preferably, within 2 months from today. No order as to costs.”
4646. After the learned APTEL passed the aforesaid order, M/s D.B. Power Ltd. (L-2 bidder) filed an Interlocutory Application before the State Commission, praying for passing forthwith consequential orders in terms of the judgment of the learned APTEL. It also sought a direction to DISCOMS to start procuring power from it to the extent of 410 MW as per the PPA dated 1st November 2013.
p. 940
Digital Supreme Court Reports
4747. When the matter was heard by the State Commission on 8th March 2018, it was noticed that appeals against the order of the learned APTEL were pending before this Court.
4848. This Court disposed of the said appeals vide judgment and order dated 25th April 2018, and issued the following directions: “We are in agreement with the earlier conclusion of the APTEL. We are of the view that the direction of reduction of capacity from 1000 mw to 500 mw by the State Commission was correctly set aside. Since L-1 to L-5 were represented before this Court, we direct that they shall be entitled to supply of power in terms of the originally offered amount, mentioned above, in accordance with para 3.5 of the Request for Proposal. The power supply will now be reduced to a total of 906 mw. The State Commission may now go into the issue of approval for adoption of tariff with regard to L-4 and L-5. All Letters of Intent (LOIs) shall stand modified in terms of the above. All the appeals shall stand disposed of in terms of the above order.”
4949. Consequent to the orders passed by this Court, the State Commission vide its order dated 29th May 2018, directed RVPN/DISCOMS to file an appropriate application/petition in relation to L-3, L-4 and L-5 bidders.
5050. RVPN accordingly filed an application on 27th August 2018 before the State Commission, submitting therein that the tariff of L-4 and L-5 bidders was very high and not aligned to market prices and, therefore, sought not to be adopted in terms of the competitive bidding guidelines and documents.
5151. In the meantime, a Contempt Petition came to be filed before this Court by SKS Power. This Court vide order dated 20th September 2018, in the said Contempt Petition, issued the following directions: “We are of the view that there is no doubt whatsoever that now the PPA has to be signed between the parties. However, the State Commission, may, as per our order, go into the issue of approval of adoption of tariff with regard to L-5, who is the party before us, and will decide the same within a period of six weeks from today.
p. 941
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
PPA is to be signed immediately thereafter.” [emphasis supplied]
5252. Thereafter, SKS Power filed an Interlocutory Application on 5th October 2018, praying for adoption of its tariff as per the orders of this Court dated 25th April 2018 and 20th September 2018.
5353. It was contended before the State Commission by SKS Power that the State Commission was bound to adopt tariff as quoted by it. However, per contra, it was contended by the RVPN and DISCOMS that since the tariff quoted by SKS Power was not market aligned, it could not be adopted. In view of the counter submission, the State Commission vide its order dated 16th October 2018, gave an opportunity to the RVPN to file an amended application or seek direction on the issue from this Court.
5454. Accordingly, RVPN filed a Miscellaneous Application before this Court. This Court vide order dated 19th November 2018, passed the following order: “Having heard learned counsels for both the parties, we only clarify that the Rajasthan Electricity Regulatory Commission [the State Commission) is to decide the tariff under-Section 63 of the Electricity Act, 2003 having regard to the law laid down both statutorily and by this Court. The State Commission to finalise the aforesaid prices within a period of eight weeks from today. The MAs are disposed of accordingly.”
5555. A review application was also filed on behalf of the SKS Power. The said review application was disposed of by this Court vide order dated 21st January 2019, with the following directions: “------. We find that as per the Standard Bidding Guidelines the PPA is first to be signed after which the question of adoption of tariff has to be taken up. With this clarification of the 20.09.2018 order, we dispose of the review and the M.A. The State Commission which has reserved its judgment
p. 942
Digital Supreme Court Reports
on 16.01.2019 will hear the parties within a period of two weeks from today and will pass orders after taking into account the order that we have passed today.”
5656. In accordance with the directions issued by this Court, the State Commission considered the rival submissions of the parties and came to a conclusion that the tariff quoted by SKS Power was not market aligned. The State Commission also found that, adoption of such high rate would be against the consumer interest. The State Commission, therefore, vide order dated 26th February 2019, decided not to adopt the tariff quoted by L-4 and L-5 bidders.
5757. The said order dated 26th February 2019 of the State Commission was challenged before the learned APTEL by SKS Power by way of Appeal No.224 of 2019. The learned APTEL framed the following three issues in the said appeal: “ISSUE NO.1: Whether the Respondent Commission could reject the tariff/bid of the Appellant, in terms of Section 63 of the Electricity Act, 2003 and the directions issued by the Hon’ble Supreme Court? ISSUE NO.2: Whether there was a sufficient proof to show that the bid of the Appellant was market aligned? ISSUE NO.3: Whether the argument of Consumer interest be advanced by the Rajasthan Discoms in the facts of the present Appeal?”
5858. The learned APTEL while answering the first issue, came to the conclusion that the State Commission, while adopting tariff under Section 63, has to only consider that the Bidding Guidelines issued by the Central Government providing for tariff structure were complied with or not. The learned APTEL also held that the State Commission cannot exercise its powers de hors such guidelines. It further held that the State Commission has no power to reject the tariff of a bidder.
5959. Insofar as the second issue is concerned, the learned APTEL came to a finding that, since the bid of SKS Power was already evaluated, and the subsequent certificates were issued by the BEC confirming
p. 943
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
the transparency of the bid, it was not open for the State Commission to go into the question, as to whether the tariff quoted by SKS Power was market aligned or not. It further held that, after the order dated 25th April 2018 was passed by this Court, it was not open for the State Commission to re-evaluate the bid.
6060. Insofar as the third issue with regard to consumers’ interest is concerned, the learned APTEL held that the said issue cannot be raised again at that stage when the same had been dealt with in detail by the learned APTEL vide order dated 2nd February 2018 and also considered by this Court before passing the order dated 25th April, 2018.
6161. Accordingly, the appeal was allowed by the learned APTEL vide order dated 3rd February 2020 and the order dated 26th February 2019 of the State Commission was set aside. The learned APTEL directed that the tariff of SKS Power, as offered in its bid, shall be adopted. The parties were directed to revive and implement the PPA dated 4th February 2019. This order dated 3rd February 2020, passed by the learned APTEL has been challenged by the DISCOMS and RVPN before this Court by way of Civil Appeal No.1937 of 2020 and Civil Appeal No. 2721 of 2020 respectively.
6262. The respondent No.1 in the present proceedings rests its claim on the aforesaid orders passed by this Court and the order dated 3rd February 2020, passed by the learned APTEL.
6363. Basically, it is the contention of the respondent No.1-MB Power that after the orders were passed by this Court, RVPN and the DISCOMS were bound to procure electricity/power from the bidders going down the ladder until the entire 906 MW power was exhausted. It is their contention that once it is certified that the bid evaluation process has been complied with as per the Bidding Guidelines issued by the Central Government, it is presumed that the process was transparent and it is not permissible for the State Commission to go into the question of market aligned tariff and also the consumer interest. It is their contention that without considering the question, as to whether the tariff was market aligned or not, the procurers were bound to accept supply from the bidders at the rates quoted by them. It is their submission that the power under Section 63 of the Electricity
p. 944
Digital Supreme Court Reports
Act restricted the scrutiny only to two aspects, viz., (1) whether the Bidding Guidelines framed by the Union of India under Section 63 of the Electricity Act were followed; and (2) whether the bidding process was transparent or not.
6464. The High Court in the impugned judgment, relying on the observations of the learned APTEL and the earlier orders of this Court has come to a conclusion that, applying the test of “filling the bucket”, the procurers were bound to take supply from the respondent No.1-MB Power at the rates quoted by it. On the basis of the judgment of the learned APTEL, the High Court held that the respondent No.1-MB Power had a right to supply power since there was a gap of 300 MW between the power procured by the procurers and the ceiling of 906 MW determined by this Court. In these premises, the High Court issued a mandamus directing the appellants to take supply of 200 MW electricity/power from the respondent No.1-MB Power at the rates quoted by it.
6565. We, therefore, find that, before deciding the correctness or otherwise of the impugned judgment, it will be necessary for us to examine the correctness of the judgment and order dated 3rd February 2020, passed by the learned APTEL in the case of SKS Power.
6666. We have already reproduced Section 63 of the Electricity Act. The provisions of Section 63 of the Electricity Act fell for consideration before this Court in the case of Energy Watchdog (supra). It will be apposite to refer to paragraphs 19 and 20 of the said judgment, which are as under: “19. The construction of Section 63, when read with the other provisions of this Act, is what comes up for decision in the present appeals. It may be noticed that Section 63 begins with a non obstante clause, but it is a non obstante clause covering only Section 62. Secondly, unlike Section 62 read with Sections 61 and 64, the appropriate Commission does not “determine” tariff but only “adopts” tariff already determined under Section 63. Thirdly, such “adoption” is only if such tariff has been determined through a transparent process of bidding, and, fourthly, this transparent process of bidding must be in accordance with the guidelines issued by the Central Government.
p. 945
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
What has been argued before us is that Section 63 is a standalone provision and has to be construed on its own terms, and that, therefore, in the case of transparent bidding nothing can be looked at except the bid itself which must accord with guidelines issued by the Central Government. One thing is immediately clear, that the appropriate Commission does not act as a mere post office under Section 63. It must adopt the tariff which has been determined through a transparent process of bidding, but this can only be done in accordance with the guidelines issued by the Central Government. Guidelines have been issued under this section on 19-1-2005, which guidelines have been amended from time to time. Clause 4, in particular, deals with tariff and the appropriate Commission certainly has the jurisdiction to look into whether the tariff determined through the process of bidding accords with Clause 4.
20. It is important to note that the regulatory powers of the Central Commission, so far as tariff is concerned, are specifically mentioned in Section 79(1). This regulatory power is a general one, and it is very difficult to state that when the Commission adopts tariff under Section 63, it functions dehors its general regulatory power under Section 79(1)(b). For one thing, such regulation takes place under the Central Government’s guidelines. For another, in a situation where there are no guidelines or in a situation which is not covered by the guidelines, can it be said that the Commission’s power to “regulate” tariff is completely done away with? According to us, this is not a correct way of reading the aforesaid statutory provisions. The first rule of statutory interpretation is that the statute must be read as a whole. As a concomitant of that rule, it is also clear that all the discordant notes struck by the various sections must be harmonised. Considering the fact that the non obstante clause advisedly restricts itself to Section 62, we see no good reason to put Section 79 out of the way altogether. The reason why Section 62 alone has been put out of the way is that determination of tariff can take place in one of two ways — either under Section
p. 946
Digital Supreme Court Reports
62, where the Commission itself determines the tariff in accordance with the provisions of the Act (after laying down the terms and conditions for determination of tariff mentioned in Section 61) or under Section 63 where the Commission adopts tariff that is already determined by a transparent process of bidding. In either case, the general regulatory power of the Commission under Section 79(1) (b) is the source of the power to regulate, which includes the power to determine or adopt tariff. In fact, Sections 62 and 63 deal with “determination” of tariff, which is part of “regulating” tariff. Whereas “determining” tariff for inter- State transmission of electricity is dealt with by Section 79(1)(d), Section 79(1)(b) is a wider source of power to “regulate” tariff. It is clear that in a situation where the guidelines issued by the Central Government under Section 63 cover the situation, the Central Commission is bound by those guidelines and must exercise its regulatory functions, albeit under Section 79(1)(b), only in accordance with those guidelines. As has been stated above, it is only in a situation where there are no guidelines framed at all or where the guidelines do not deal with a given situation that the Commission’s general regulatory powers under Section 79(1)(b) can then be used.” [emphasis supplied]
6767. It could thus be seen that it has been held by this Court that unlike Section 62 read with Sections 61 and 64, under the provisions of Section 63 of the Electricity Act, the appropriate Commission does not “determine” tariff but only “adopts” tariff already determined under Section 63. It has further been held that, such “adoption” is only if such tariff has been determined through a transparent process of bidding, and that, this transparent process of bidding must be in accordance with the guidelines issued by the Central Government. It was sought to be contended before this Court in the said case that Section 63 is a standalone provision and has to be construed on its own terms, and that, therefore, in the case of transparent bidding nothing can be looked at except the bid itself which must accord with guidelines issued by the Central Government. However, rejecting the said contention, this Court observed that the appropriate
p. 947
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
Commission does not act as a mere post office under Section 63. It has been observed that, Clause 4, in particular, deals with tariff and the appropriate Commission certainly has the jurisdiction to look into whether the tariff determined through the process of bidding accords with Clause 4.
6868. This Court in the said case, in paragraph 20, further observed that the entire Act shall be read as a whole. It has been held that, all the discordant notes struck by the various sections must be harmonized. It has been held that, considering the fact that the non obstante clause advisedly restricts itself to Section 62, there is no reason to put Section 79 out of the way altogether. It has been held that, either under Section 62, or under Section 63, the general regulatory power of the Commission under Section 79(1)(b) is the source of the power to regulate, which includes the power to determine or adopt tariff. It has been held that, Sections 62 and 63 deal with “determination” of tariff, which is part of “regulating” tariff. It has further been held that, in a situation where the guidelines issued by the Central Government under Section 63 cover the situation, the Central Commission is bound by those guidelines and must exercise its regulatory functions, albeit under Section 79(1)(b), only in accordance with those guidelines. It has further been held that, it is only in a situation where there are no guidelines framed at all or where the guidelines do not deal with a given situation that the Commission’s general regulatory powers under Section 79(1)(b) can be used.
6969. The aforesaid view of this Court in the case of Energy Watchdog (supra), which is a judgment delivered by two Judge Bench, has been approved by three Judge Bench of this Court in the case of Tata Power Company Limited Transmission (supra).
7070. We have already referred to Section 86(1)(b) of the Electricity Act, which is analogous to Section 79 of the Electricity Act. Section 79 determines the functions of Central Commission, whereas Section 86 provides for the functions of the State Commission. Section 86 of the Electricity Act empowers the State Commission to regulate electricity purchase and procurement process of distribution licensees including the price at which electricity shall be procured from the generating companies or licensees or from other sources through agreements for purchase of power for distribution and supply within the State.
p. 948
Digital Supreme Court Reports
7171. It can thus be seen that Section 86(1)(b) of the Electricity Act gives ample power on the State Commission to regulate electricity purchase and procurement process of distribution licensees. It also empowers the State Commission to regulate the matters including the price at which electricity shall be procured from the generating companies, etc.
7272. It will also be relevant to refer to the Bidding Guidelines notified by the Central Government vide Resolution dated 19th January 2005. The preamble of the Bidding Guidelines specifically states that, one of the objectives of the said Bidding Guidelines is to facilitate transparency and fairness in procurement processes and protection of consumer interests by facilitating competitive conditions in procurement of electricity.
7373. Clause 5.15 of the Bidding Guidelines is an important clause. It provides that, the bidder who has quoted lowest levelized tariff as per evaluation procedure, shall be considered for the award. It also provides that the evaluation committee shall have the right to reject all price bids if the rates quoted are not aligned to the prevailing market prices.
7474. It is thus amply clear that the evaluation committee is empowered to consider, as to whether the rates quoted are aligned to the market price or not, and that the evaluation committee shall have the right to reject all the price bids if it finds that the rates quoted are not aligned to the prevailing market price. The orders which are relied upon by the learned APTEL, specifically the order dated 19th November 2018 of this Court, had specifically clarified that the State Commission was to decide the tariff under Section 63 of the Electricity Act having regard to the law laid down both statutorily and by this Court.
7575. In this background, the State Commission was justified in considering clause 5.15 of the Bidding Guidelines, which specifically permits to reject all price bids if the rates quoted are not aligned to the prevailing market prices.
7676. The contention that this Court has ordered that the bids quoted by the bidders are to be accepted without going into the question of it being market aligned or not, in our view, is without substance.
7777. If the contention of the respondent No.1-MB Power that the procurer is bound to accept all the bids emerged in a competitive bidding
p. 949
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
process once the bidding process was found to be transparent and in compliance with the Bidding Guidelines is to be accepted, in our view, it will do complete violence to clause 5.15 of the Bidding Guidelines itself. If that view is accepted, the DISCOMS will be compelled to purchase electricity at a much higher rate as compared with other suppliers. The said higher rate will be passed on to the consumers. As such, accepting the contention of the respondent No.1 would result in adversely affecting the interests of the consumers and, in turn, would be against the larger public interest. For example, if in a bidding process for 1000 MW power, 10 persons emerged as “qualified bidders”. L-1 bidder quotes Rs.2 per unit for 100 MW power and L-2 bidder quotes Rs.2.25 per unit for another 100 MW power and from L-3 bidder onwards, they start quoting Rs.10 per unit and above for balance 800 MW power, could the public interest be subserved by compelling the procurer to buy balance 800 MW power at Rs.10 per unit and above when the prices quoted are totally not aligned to market prices.
7878. We are, therefore, of the considered view that the learned APTEL has grossly erred in holding that the State Commission has no power to go into the question, as to whether the prices quoted are market aligned or not and also not to take into consideration the aspect of consumers’ interest.
7979. When the Bidding Guidelines itself permit the BEC to reject all price bids if the rates quoted are not aligned to the prevailing market prices, there is no question of the State Commission being not in a position to go into the question, as to whether the rates quoted are market aligned or not, specifically, in the light of ample powers vested with the State Commission under Section 86(1)(b) of the Electricity Act, which also includes the power to regulate the prices at which electricity shall be procured from the generating companies, etc. The finding of the learned APTEL, in our view, therefore, is totally erroneous.
8080. In the case of SKS Power, the BEC, consisting of following 6 members, has considered the levelized tariff quoted by L-4 and L-5 bidders: (i) Shri R.K. Jain, Chief Engineer (NPP & RA), RVPN, Jaipur; (ii) Shri Manish Saxena, Chief Controller of Accounts, RVPN, Jaipur; (iii) Shri M.M. Ranwa, Chief Engineer, RUVNL, Jaipur; (iv) Shri K.L. Meena, Addl. Chief Engineer (Fuel), RVUN, Jaipur; (v) Shri S.K. Mathur, Chief Engineer (HQ), JVVNL, Jaipur; and
p. 950
Digital Supreme Court Reports
(vi) Shri Tarun Agarwal, CA, Partner M/s Shyamlal Agrawal & Co., Jaipur
8181. It can be seen that the said Committee consisted of 4 technical members of the rank of Chief Engineer/Additional Chief Engineer. It consisted of the Chief Controller of Account, RVPN, Jaipur. It also consisted of a Chartered Accountant, who is an expert in financial matters. After due deliberations, the BEC consisting of experts found that the prices quoted by L-4 and L-5 bidders were exorbitantly high and it would result in additional financial burden of more than Rs.1715 crore on the consumers of the State as compared to the tariff of L-1 bidder.
8282. The State Commission after considering the detailed analysis of the BEC had come to the considered conclusion that the prices offered by SKS Power (L-5 bidder) were not market aligned, and therefore, not in the consumers’ interest. We, therefore, find that the learned APTEL has grossly erred in reversing the well-reasoned order passed by the State Commission, which was, in turn, based on the decision of the BEC in accordance with clause 5.15 of the Bidding Guidelines.
8383. We further find that it cannot be read from the orders of this Court that the State Commission was bound to accept the bids as quoted by the bidders till the bucket was filled. Firstly, no such direction can be issued by this Court de hors the provisions of Section 63 and 86(1)(b) of the Electricity Act and the Bidding Guidelines. In any event, vide order dated 19th November 2018, this Court had specifically directed the State Commission to decide the tariff under Section 63 of the Electricity Act having regard to the law laid down both statutorily and by this Court. As such, the State Commission was bound to take into consideration the Bidding Guidelines and specifically clause 5.15 thereof.
8484. With regard to the contention that the power under clause 5.15 of the Bidding Guidelines can be exercised only when the bidding process is found to be not in compliance with the Bidding Guidelines and is not transparent in respect of all the bidders and not in respect of some of the bidders is concerned, in our view, the same is without substance.
8585. We may in this respect refer to Section 13(2) of the General Clauses Act, which reads thus:
p. 951
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
“13. Gender and number.—In all Central Acts and Regulations, unless there is anything repugnant in the subject or context,— (1) …………………; and (2) words in the singular shall include the plural, and vice versa.”
8686. Apart from that, the Constitution Bench of this Court in the case of Vivek Narayan Sharma and others v. Union of India and others10 had an occasion to consider the question, as to whether the word “any” would include “all” and vice versa. The Constitution Bench of this Court observed thus: “113. It is strenuously urged by the learned Senior Counsel appearing on behalf of the petitioners that the word “any” used in sub-section (2) of Section 26 of the RBI Act will have to be given a restricted meaning to mean “some”. It is submitted that if sub-section (2) of Section 26 of the RBI Act is not read in such manner, the very power available under the said sub-section will have to be held to be invalid on the ground of excessive delegation. It is submitted that it cannot be construed that the legislature intended to bestow uncanalised, unguided and arbitrary power on the Central Government to demonetise the entire currency. It is, therefore, the submission of the petitioners that in order to save the said section from being declared void, the word “any” requires to be interpreted in a restricted manner to mean “some”.
114. Per contra, it is submitted on behalf of the respondents that the word “any” under sub-section (2) of Section 26 of the RBI Act, cannot be interpreted in a narrow manner and it will have to be construed to include “all”. Precedents construing the word “any”
115. A Constitution Bench of this Court in Chief Inspector of Mines v. Lala Karam Chand Thapar [Chief Inspector of Mines v. Lala Karam Chand Thapar, (1962) 1 SCR 9 : AIR 1961 SC
Footnotes
p. 952
Digital Supreme Court Reports
838] was considering the question as to whether the phrase “any one of the Directors” as found in Section 76 of the Mines Act, 1952 could mean “only one of the Directors” or could it be construed to mean “every one of the Directors”. In the said case, all the Directors of the Company were prosecuted for the offences punishable under Sections 73 and 74 of the Mines Act,
1952. The High Court had held [Lala Karam Chand Thapar v. State of Bihar, 1958 SCC OnLine Pat 30] that any “one” of the Directors of the Company could only be prosecuted.
116. The Constitution Bench of this Court observed thus : (Lala Karam Chand Thapar case [Chief Inspector of Mines v. Lala Karam Chand Thapar, (1962) 1 SCR 9 : AIR 1961 SC 838], AIR pp. 847-48, paras 29-34) “29. It is quite clear and indeed not disputed that in some contexts, “any one” means “one only it matters not which one” the phrase “any of the Directors” is therefore quite capable of meaning “only one of the Directors, it does not matter which one”. Is the phrase however capable of no other meaning? If it is not, the courts cannot look further, and must interpret these words in that meaning only, irrespective of what the intention of the legislature might be believed to have been. If however the phrase is capable of another meaning, as suggested viz. “every one of the Directors” it will be necessary to decide which of the two meanings was intended by the legislature.
30. If one examines the use of the words “any one” in common conversation or literature, there can be no doubt that they are not infrequently used to mean “every one” — not one, but all. Thus we say of any one can see that this is wrong, to mean “everyone can see that this is wrong”. “Any one may enter” does not mean that “only one person may enter”, but that all may enter. It is permissible and indeed profitable to turn in this connection to Oxford English Dictionary, at p. 378, of which, we find the meaning of “any” given thus:‘In affirmative sentences, it asserts, concerning a being or thing of the sort named, without limitation as to which, and thus collectively of
p. 953
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
every one of them’. One of the illustrations given is — “I challenge anyone to contradict my assertions”. Certainly, this does not mean that one only is challenged; but that all are challenged. It is abundantly clear therefore that “any one” is not infrequently used to mean “every one”.
31. But, argues Mr Pathak, granting that this is so, it must be held that when the phrase “any one” is used with the preposition “of”, followed by a word denoting a number of persons, it never means “every one”. The extract from Oxford Dictionary, it is interesting to notice, speaks of an assertion “concerning a being or thing of the sort named”; it is not unreasonable to say that, the word “of” followed by a word denoting a number of persons or things is just such “naming of a sort” as mentioned there. Suppose, the illustration “I challenge any one to contradict my assertions” was changed to “I challenge any one of my opponents to contradict my assertion”. “Any one of my opponents” here would mean “all my opponents” — not one only of the opponents.
32. While the phrase “any one of them” or any similar phrase consisting of “any one”, followed by “of” which is followed in its turn by words denoting a number of persons or things, does not appear to have fallen for judicial construction, in our courts or in England — the phrase “any of the present Directors” had to be interpreted in an old English case, Isle of Wight Railway Co. v. Tahourdin [Isle of Wight Railway Co. v. Tahourdin, (1883) LR 25 Ch D 320 (CA)] . A number of shareholders required the Directors to call a meeting of the company for two objects. One of the objects was mentioned as ‘To remove, if deemed necessary or expedient any of the present Directors, and to elect Directors to fill any vacancy on the Board’. The Directors issued a notice to convene a meeting for the other object and held the meeting. Then the shareholders, under the Companies Clauses Act, 1845, issued a notice of their own convening a meeting for both the objects in the original requisition. In an action by the Directors to
p. 954
Digital Supreme Court Reports
restrain the requisitionists, from holding the meeting, the Court of Appeal held that a notice to remove “any of the present Directors” would justify a resolution for removing all who are Directors at the present time. “Any”, Lord Cotton, L.J. pointed out, would involve “all”.
33. It is true that the language there was “any of the present Directors” and not “any one of the present Directors” and it is urged that the word “one”, in the latter phrase makes all the difference. We think it will be wrong to put too much emphasis on the word “one” here. It may be pointed out in this connection that the Permanent Edition of Words and Phrases, mentions an American case Front & Huntingdon Building & Loan Assn. v. Berzinski [Front & Huntingdon Building & Loan Assn. v. Berzinski, 130 Pa Super 297 : 196 A 572 (Superior Court of Pennsylvania 1938)] where the words “any of them” were held to be the equivalent of “any one of them”.
34. After giving the matter full and anxious consideration, we have come to the conclusion that the words “any one of the Directors” is ambiguous; in some contexts, it means “only one of the Directors, does not matter which one”, but in other contexts, it is capable of meaning “every one of the Directors”. Which of these two meanings was intended by the legislature in any particular statutory phrase has to be decided by the courts on a consideration of the context in which the words appear, and in particular, the scheme and object of the legislation.” (emphasis supplied)
117. The Constitution Bench in Lala Karam Chand Thapar case [Chief Inspector of Mines v. Lala Karam Chand Thapar, (1962) 1 SCR 9 : AIR 1961 SC 838] found that the words “any one” have been commonly used to mean “every one” i.e. not one, but all. It found that the word “any”, in affirmative sentences, asserts, concerning a being or thing of the sort named, without limitation. It held that it is abundantly clear that the words “any one” are not infrequently used to mean “every one”.
p. 955
Jaipur Vidyut Vitran Nigam Ltd. & Ors. v. MB Power (Madhya Pradesh) Limited & Ors.
118. It could be seen that the Constitution Bench in Lala Karam Chand Thapar case [Chief Inspector of Mines v. Lala Karam Chand Thapar, (1962) 1 SCR 9 : AIR 1961 SC 838], after giving the matter full and anxious consideration, came to the conclusion that the words “any one of the Directors” was an ambiguous one. It held that in some contexts, it means “only one of the Directors, does not matter which one”, but in other contexts, it is capable of meaning “every one of the Directors”. It held that which of these two meanings was intended by the legislature in any particular statutory phrase has to be decided by the courts on consideration of the context in which the words appear, and in particular, the scheme and object of the legislation.
119. After examining the scheme of the Mines Act, 1952, the Constitution Bench of this Court further observed thus : (Lala Karam Chand Thapar case [Chief Inspector of Mines v. Lala Karam Chand Thapar, (1962) 1 SCR 9 : AIR 1961 SC 838], AIR pp. 848-49, paras 36-38) “36. But, argues Mr Pathak, one must not forget the special rule of interpretation for “penal statute” that if the language is ambiguous, the interpretation in favour of the accused should ordinarily be adopted. If you interpret “any one” in the sense suggested by him, the legislation he suggests is void and so the accused escapes. One of the two possible constructions, thus being in favour of the accused, should therefore be adopted. In our opinion, there is no substance in this contention. The rule of strict interpretation of penal statutes in favour of the accused is not of universal application, and must be considered along with other well-established rules of interpretation. We have already seen that the scheme and object of the statute makes it reasonable to think that the legislature intended to subject all the Directors of a company owning coal mines to prosecution and penalties, and not one only of the Directors. In the face of these considerations there is no scope here of the application of the rule for strict interpretation of penal statutes in favour of the accused.
37. The High Court appears to have been greatly impressed by the fact that in other statutes where the
p. 956
Report an error in this judgment →
Contains information from the Indian High Court / Supreme Court Judgments dataset, licensed under CC-BY-4.0