A memorandum. Once award has been passed on taking possession under Section 16 of the Act of 1894, the land vests in State there is no divesting provided under Section 24(2) of the Act of 2013, as once possession has been taken there is no lapse under Section 24(2).
8. The provisions of Section 24(2) providing for a deemed lapse B of proceedings are applicable in case authorities have failed due to their inaction to take possession and pay compensation for five years or more before the Act of 2013 came into force, in a proceeding for land acquisition pending with concerned authority as on 1.1.2014. The period of subsistence of interim orders passed by court has to be excluded in the computation of five years. C
9. Section 24(2) of the Act of 2013 does not give rise to new cause of action to question the legality of concluded proceedings of land acquisition. Section 24 applies to a proceeding pending on the date of enforcement of the Act of 2013, i.e., 1.1.2014. It does not revive stale and time-barred claims and does not reopen concluded proceedings nor D allow landowners to question the legality of mode of taking possession to reopen proceedings or mode of deposit of compensation in the treasury instead of court to invalidate acquisition. Let the matters be placed before appropriate Bench for consideration on merits. E
Devika Gujral Reference answered.
Report an error in this judgment →