INDIA METERS LTD., MADRAS v. PUNJAB STATE ELECTRICITY BOARD AND ORS.

vidhipandit.com/case/sc-s-1992-1-309-316

Supreme Court of India (SC) · decided (year only) · N.M. KASLIWAL and K. RAMASWAMY · judgment

Decision dates shown here are day-precision where the judgment's own text states a date the extractor is confident in, and year only otherwise -- never a fabricated day. See the editorial policy for how dates are extracted.

[1992] Supp. 1 S.C.R. 309

Headnote — Supreme Court Reports (editorial summary, not part of the judgment)

Held

1. There was no concluded contract between the parties and as such the respondent-Board was not entitled to enforce the arbitration clause. The High Court was not correct in holding that the subsequent correspondence regarding the security deposit, mode of payment and samples were merely consequential steps taken in furtherance of the implementation of the contract and the contract already stood concluded between the parties. The mode of payment which included the furnishing of bank guarantee was an important term and condition of the contract as ...,11 as the furnishing of the samples. The appellant by its letter dated 24.3.1978 made its offer and had clearly put its own terms and conditions as regards the furnishing of bank guarantee and the Board never con· curred on those terms, rather in their letter dated 30.8.1978 clearly turned down the request of the appellant. Thus there was no concluded contract between the parties. [315 G·H; 316 A·B]

Reporter's headnote (continued) and case details

SEPTEMBER 2, 1992 B

Arbitration Act, 1940:

Section 3rArbitration clause provided in the purchase order-cum-con- tract-Terms and conditions regarding payment not mentioned-Supplier in- C sisting on its own term?-l'urchaser not agreeing-Subsequent comspon- dence-Effect of-Whether contract concluded between parties-rlrbitration cluase-Whether could be enforced.

In response to a tender notice issued by tbe Respondent-Electricity D Board, the appellant offered to supply tbeir standard electricity meters and stipulated their own terms of payment. It also Indicated tbat it will not submit a bank guarantee as demanded in the tender notice. Sub- sequently tbe appellant sent a telegram reiterating the offer, keeping all tbeir terms and conditions unaltered. E The Respondent-Board sent a purchase order-cum-contract for supply of 75,000 meters. In tbe order, tbere was no reference to the terms and conditions or payment including tbe furnishing of bank guarantee. It was stipulated that tbe meters supplied. by the appellant would be ac· cepted subject to furnishing or sampies. It was also stipulated tbat dis· F pules, if any, would be. referred to the sole arbitration or a nominee of the Board. After exchange or series of correspondence, the Respondent-Board did not agree to tbe original offer of the appellant, as also its requests regarding acceptance of a bank guarantee or Rs. 1 lakh towards 100% payment and security deposit. Thereafter, the appellant informed tbe Board tbat it was not In a position to take furtber action in the tender and G tbe production planning had been dropped.

The Board appointed an arbitrator, and filed its claim towards damages on account of tbe alleged breach or contract made by the appel- lant. H 309

310 SUPREME COURT REPORTS[1992] SUPP. 1 S.C.R.

A The appellant Died an application under section 33 of the Arbltra· lion Act before the Sub-Judge alleging that there was no completed con· tract between the parties. The Sub-Judge allowed the application and restrained the Arbitrator from proceeding further in the arbitration.

The Respondent-Board preferred an appeal under section 39 of the B Arbitration Act before the High Court. Treating it as a Revision Petition, the High Court held that the appellant bad accepted the offer of the Board and thereafter the Board by their letter dated 27.7.1978 had placed the purchase order. It further held that the subsequent correspondence regarding the security deposit, mode of payment and samples were merely consequential steps taken in furtherance of the implemeutation of the contract aud they do not in any manner undermine the contract which othenrise stood concluded between the parties. Against this order of the High Court the appellant filed the present appeal.

On the question as to whether there was any concluded contract between the parties:

Allowing the appeal, this Court,

2. The appellant at the relevant time was a sick unit and steps were being taken to revive the same through a Government undertaking. Under these circumstances if the appellant was insisting on giving exemption from furnishing bank guarantee, it cannot be said that its action was

INDIA METERS v. ELECTRICITY BOARD [KASLIWAL, J.] 311 unjustified. [316 B·CJ A CIVIL APPELLATE JURISDICTION :-Civil Appeal No. 3496 of 1992.

From the Judgment and Order dated 23.4.91 of the Madras High Court in C.M.P. No. 2111 of 19S4. B R.F. Nariman, Ms. V.S. Rekha, H.S. Anand and Hardeep Singh Anand for the Appellant.

Sarup Singh and Arun Madan for the Respondents. c

Judgment

The Judgment of the Court was delivered by

KASLIWAL, J. Special Leave granted.

This appeal by Mis India Meters Ltd., hereinafter referred to as the Appellant is directed against the Judgment of the High Court of Judicature D at Madras dated 23.4.1991.

The Punjab State Electricity Board issued a tender notice by publi- cation in the newspaper Indian Express dated 24.2.1978, inviting sealed ·· · tenders form supply of house service electricity meters and Amps. The E appellant offered to supply their standard meier type OB-7 and stipulated their own terms of payment and indicated that they would not submit a bank guarantee as demanded in the tender notice. The appellant also ser.t a telegram on 3.6.1978, reiterating the offer to supply the meters, keeping all their terms and conditions unaltered. F The Board vide their communication dated 27.7.1978 sent a purchase order-cum-contract for supply of 75000 meters. In this purchase order no reference was made to the terms and condition of ·payment and the inability to furnish bank guarantee by the apppellant. In clause 20 of the purchase order the Board further mentioned that the meters supplied by the appel- lant would be accepted subject to the furnishing of samples. In Clause 26 G it was mentioned that disputes, if any, would be referred to the sole arbitration of a nominee of the Board. The appellant by letter dated 19.8.1978 informed the Board that samples had already been sent, and that fresh samples could not be insisted upon and called upon the Board to send their acceptance of the offer made by the appellant on the basis of H

312 SUPREME COURT REPORTS[1992] SUPP. 1 S.C.R.

A the terms laid down by the appellant. The Board by its letter dated 30.8.1978 sent a reply stating that exemption from bank guarantee was not acceptable to them and called upon the appellant to send the samples again. The appellant then vide their letter dated 7.11.1978 informed the Board that they had been granted exemption from furnishing security B deposit and bank guarantee for the various purchase orders placed by Tamil Nadu Electricity Board and Haryana State Electricity Board. It was also stated that the factory of the appellant was under revival and it had been declared as a relief undertaking by Government of Tamil Nadu. It was further mentioned that inspite of explaining special circumstances that appellant is a sick industry and· is striving to revive with the support from C Government institutions, it was understood that the Punjab State Electricity BC1ard was unable to agree to the original offer of the appellant and repeated requests made regarding acceptance of a bank guarantee of rupees one lakh toward 1(10% payment and security deposit and in the absence of such concurrence the appellant was not in a position to take further action in the tender and production planning had been dropped. Thereafter the Board by letter dated 23.12.1979 informed the appellant that the Board and appointed Sh. A.N. Sharma, Suprintending Engineer(f & MR Punjab State Electricity Board (respondent No.2) as an arbitrator. On 25.1.1980 the appellant received a copy of the claim made by the Board before the arbitrator claiming Rs.48,61,458 as damages for the alleged breach of contract made by the appellant.

The appellant then filed a application under Section 33 of the Arbitra- tion Act alleging that there was no completed contract between the parties. The offer made by the appellant was subject to their own terms and condi- F tions which were not accepted by the Board. The terms and conditions for the supply of the meters as made by the Board were not accepted by the appellant at any time. There was no consensus ad-idem and there was no completed contract. Since there was no completed contract between the appellant and the Board, there was no arbitration agreement between the parties. The appellant in these circumstances prayed for an order declaring that there was no arbitration agreement between the appellant and the Board. It was also prayed that a permanent injunction may be granted restraining the arbitrator from proceeding with the arbitration.

The Learned Subordinate Judge by his order dated 5.9.1981 allowed the application filed under Section 33 of the Arbitration Act (hereinafter

INDIA METERS v. ELECTRICITY BOARD [KASLIWAL, J.] 313

referred to as to 'Act') and restrained the arbitrator, respondent no.2 from further proceedings in the arbitration. The Board aggrieved against the order of the Learned Subordinate Judge filed an appeal before the High Court under Section 39 of the Act. The High Court though agreed with the objection raised on behalf of M/s India Meters Ltd., that appeal under Section 39(1) of the Act was not maintainable, but took the view that the matter could be considered as a revision under Section 115 of the Civil B Procedure Code. The High Court accepted the plea of the Board in this regard and ordered that the appeal filed in the case may be converted and treated as revision filed under Section 115 C.P.C and thereafter examined the merits of the case. The High Court allowed the revision after holding that the appellant had accepted the offer of the Board and thereafter the C Board vide their letter dated 27.7.1978 had placed the purchase order cum contract for the supply of 75000 meters. The High Court further held that the subsequent correspondence regarding the security deposit, mode of payment and samples were merely consequential steps taken in furtherance of the implementation of the contract and· they do not in any manner D undermine the contract which otherwise stood concluded between the parties as could be seen from Ell. A-7 (dated 27.7.78) and Ex. A-8 (dated 7.11.78). The High Court ultimately set aside the order of the Subordinate Judge and directed that the arbitrator shall be at liberty to proceed with the matter after giving sufficient and effective opportunity to the appellant. Mis India Meter Ltd. aggrieved against the Judgment of the High Court E has filed the above appeal

We have heard learned counsel for the parties and have thoroughly perused the record. The parties have placed on record the entire cor- respondence which took place between the parties necessary for resolving the controversy. The appellant in their letter dated 24th March, 1978 itself in Clauses 10 artd 12 mentioned as under:

Clause 10: PAYMENT:

We request you to make 100% payment along with full payment of sales-tax and Excise duty etc., against R/R or L/R through Bank. We further request that the requirement of furnishing a Bank guarantee equivalent to 1% value of the order valid for two months from the date of last despatch may please be waived of a special case. Messrs. Bharat Heavy Electricals Limited, a Govt. of India Undertaking, have come forwara to H

314 SUPREME COURT REPORTS[l992] SUPP. 1 S.C.R.

A revive this "Sick Unit" and in the present Financial position of the company, this requirement may not be insisted upon.

Clause 12: EARNEST MONEY DEPOSIT AND SECURITY DEPOSIT:

B Mis Bharat Heavy Electricals Limited a Government of India Un- dertaking has since taken over the management of India Meters Limtied, being a sick unit, Earnest Money Deposit has already been exempted by all the other Electricity Boards like Tamil Nadu Electricity Board, Madhya' Pradesh Electricity Board, Haryana State Electricity Board, etc. It is C requested that you may kindly exempt us from making the above mentioned payment as a speacial case. In this connection, we invite your kind attention to our letter No.SD/PSEB/632178 dated 7.3.1978 requesting you to exempt us from making the payment.

The appellant while agreeing to supply the meters had clearly men- D tioned though in the form of request, that the appellant was a sick unit and Mis Bharat Heavy Electricals Ltd., a Government of India undertaking have come forward to revive the sick unit and as such in the present financial position of the company the requirement of furnishing a bank guarantee may not be insisted upon. The Board without settling the above- E mentioned condition placed a puchase order cum contract vide their letter dated 27.7.1978 reiterating their own terms of payment which included furnishing of bank guarantee. The appellant then vide their letter dated 19.8.1978 again requested the Board for consideration and favourable action in the following terms:- F 'We had also vide our offer No.SD/PS&Bn18/D/243.1978 requested you for 100% payment through bank against railway receipt, exempting us from fumsihing a separate deposit towards the same. Further we had agreed to furnish the necessary security deposit, as required by you. Hence, G we may now request once again to kindly exempt us from furnishing a Bank· Guarantee aginst 100% payment".

It was further mentioned that the Board may accept a permanent bank guarantee for a value of rupees one lakh only which could go a long way in helping the appellant unit. As regards sample it was clearly men-

INDIA METERS v. ELECTRICITY BOARD [KASLIWAL, J.] 315

tioned in this letter that the appellant had submitted samples already against the tender and as such requested the Board not to insist on fresh samples again. The Chief Engineer of the Board then vide letter dated 30.8.1978 clearly mentioned that as regards the terms of payment the request of the appellant regarding the exemption from furnishing a guaran- tee against 100% payment and furnishing a permanent bank guarantee of rupees one lakh towards 100% payment etc., had been considered and rejected. As regards the samples it was mentioned in this letter that the appellant had submitted only one sample meter of 2.5 Amps rating against tender enquiry No.Q-2185, whereas the order had been placed for the supply of meters of 5- 10 Amps and 10-20 Amps ratings. It was thus again requested to submit the samples of the above capacities at once in accord- C ance with Clause 20 as already requested in the earlier letter. The Super- intending Engineer also by another letter informed the appellant that the samples may please be got approved from their office before commencing the supply as mentioned under Clause 20 of the purchase order. The appellant then vide their letter dated 7.11.1978 addressed to the Chief D Engineer again took the stand that the appellant factory was under revival and had been declared as a Relief Undertaking by the Government of Tamil Nadu and that they had conveyed their acceptance to furnish a permanent bank guarantee for a value of rupees one lakh towards 100% payment as a security deposit. It was further mentioned that in the absence of the concurrence on the above condition the appellant was not in a E position to take any further action in the tender and production planning has been dropped. As regards the supply of the sample meters, the appellant reiterated its earlier stand. Thereafter the Board did not make any further correspondence nor agreed to the counter offer made by the appellant in respect of the furnishing of the bank guarantee and sending the samples and the Board resorted to the enforcement of the arbitration Clause and appointed the respondent No.2 as an arbitrator.

We have taken into consideration the entire correspondence made between the parties referred to above and we are clearly of the view that there was no concluded contract between the parties and as such the respondent Board was not entitled to enforce the arbitration clause. The High Court was not correct in holding that the subsequent correspondence regarding the security deposit, mode of payment and samples wer merely consequential steps taken in furtherance of the implementation of the contract and the contract already stood concluded between the parties. H

316 SUPREME COURT REPORTS[1992] SUPP. 1 S.C.R.

A The mode of payment which included the furnishing of bank guarantee was an important term and condition of the contract as well as the furnishing of the samples. The appellant in the its offer made vide their first letter dated 24.3.1978 had clearly put their own terms and conditions as regards the furnishing of bank guarantee and the Board never concurred on those terms, rather in their letter dated 30.8.78 clearly turned down the request of the appellant. Thus there was no concluded contract between the parties. It is not disputed that the appellant at the relev&nl time was a sick unit and the steps were being taken to revive the same through Bharat Heavy Electricals Limited, a Government of India undertaking and in those circumstances if the appellant was insisting on giving exemption from furnishing bank guarantee, it cannot be said that its action was unjustified. Thus in the circumstances mentioned above we do not agree with the view taken by the High Court.

In the result we allow this appeal, set aside the Judgment of the High Court dated 23.4.91 and affirm the decision of the Subordinate Judge. In D the circumstances of the case we direct the parties to bear their own costs.

G.N. Appeal allowed.

Report an error in this judgment →

Contains information from the Indian High Court / Supreme Court Judgments dataset, licensed under CC-BY-4.0