Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.
Tools
- Court
- Supreme Court of India
- Decided
- Citation
- 2026 INSC 1098 · S.C.R. reference pending
No public source-PDF link for this document.
Judgment
2026 INSC 1098 REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL ORIGINAL JURISDICTION
ARBITRATION PETITION (CIVIL) NO.7 OF 2025
Shubham Equipment Private Limited & Anr. .… Petitioner(s)
Versus
Rothwell Water Company Limited & Ors. …. Respondent(s)
WITH
ARBITRATION PETITION (CIVIL) NO.8 OF 2025
ORDER
Joymalya Bagchi, J.
1. Both the petitions involve same parties and raise common
questions of law and fact. Accordingly, they are being
disposed of by a common order.
2. Petitioner No. 1, Shubham Equipment Private Limited
(‘SEPL’) is an Indian company originally incorporated under
Companies Act, 1956, now governed by Companies Act,
Signature Not Verified 2013, having its registered office at Thane, Maharashtra, Digitally signed by SATISH KUMAR YADAV Date: 2026.10.08 16:01:57 IST
India. It is engaged in the business of providing services with Reason:
respect to cleaning of drinking water tanks under the trade 1
names ‘TANCLEAN’ and ‘SHUBHAM’. Petitioner No. 2, Mr.
Sunil Suresh Uplap is one of the main promoters of SEPL.
3. Respondent No. 1, Rothwell Water Company Limited (‘RWCL’)
is a company having its principal office at Gyeonggi-do,
Korea, incorporated under the Companies Act, 2012 of the
Republic of Korea. It is the holder of multiple patents in the
technology of ‘Biological Nutrient Removal Process in
Wastewater Treatment’. Respondent No. 2, Mr. Keonho Lee
is one of the main promoters and President of RWCL.
Respondent No. 3, Rothwell Business International Private
Limited (‘RBIPL’), is a wholly owned subsidiary company of
RWCL, having its registered office at Pune, Maharashtra. It
was incorporated by Respondent No. 2 along with his
daughter Ms. Ryouree Lee and one Mr. Sayaji Krishnarao
Shinde.
4. On 30.01.2019, SEPL and RWCL entered into a Technical
Collaboration Licence Agreement (‘Licence Agreement’)
whereby vide Clause 2.1 RWCL granted SEPL and/or its
affiliates an exclusive, non-transferable, royalty-bearing
license for various licensed patents relating to technology of
wastewater treatment project with specifics described more
particularly in the said Licence Agreement.
5. On 01.10.2021, a Joint Venture Agreement and Share
Holding Agreement (‘JVA’) was executed by Petitioner No.2 as
promoter/partner of SEPL and Respondent No.2 as promoter
and President of RWCL. Under the said JVA, a joint venture
company, namely, Rothwell Water (India) Private Limited
(‘RWIPL’) was created for carrying on business activities
providing for supply, installation, operation and maintenance
of latest generation sewage treatment plants and other liquid
procession products and equipment under the brand name
of ‘ROTHWELL’.
6. A perusal of the signature clause of this agreement
unequivocally shows that Petitioner No.2 affirmed the
signature on behalf of Shubham Group of Companies,
defined as the 'Indian Group'. Likewise, Respondent No.2
affirmed the signature on behalf of RWCL, i.e. defined as the
'South Korean Group', thereby signifying that the companies
of the Indian Group and South Korean Group represented
through their respective Promoter/Director signatories were
bound by the said agreement. The arbitration clause
incorporated vide Article 43 in the said JVA reads as follows:
“ART. 43. ARBITRATION (i) Any and all disputes or differences between the Parties arising out of or in connection with this Agreement or its performance shall, so far as it is possible, be settled amicably between the Parties. (ii) If after 30 days of consultation, the Parties have failed to reach an amicable settlement, on any and all disputes-or differences arising out of or in connection with this Agreement or its performance, such disputes or differences shall be referred to in arbitration in Mumbai which shall be conducted in accordance with the Law of the Republic of India which governs and protects the interest of Indian and South Korean parties respectively and any statutory modification and re-enactment thereto for the time being in force all the parties thereto irrevocably agree that the decision of the Arbitrator(s) shall be final and binding upon the parties hereto and the judgment or arbitration award may be entered in any court of competent jurisdiction. The language of the Arbitration shall be English.”
7. On 24.10.2022, a sub-contract agreement was executed
between one JWIL Infra Ltd. (‘JWIL’), having its office at New
Delhi and RWCL. On 01.02.2023, a Memorandum of
Understanding (‘MoU’) was executed between SEPL and
RWCL, inter alia, providing that SEPL would render services
like liaison with JWIL and Municipal Corporation of Greater
Mumbai on behalf of RWCL, customs clearance of goods at
Mumbai port, logistical arrangements, port handling,
transportation, warehousing, et cetera.
8. Clause 9 of the said MoU provided for dispute resolution via
arbitration, as follows:
“9.0 DISPUTE RESOLUTION 9.1 In case of any dispute or difference arising between the parties as to the interpretation or effect of this Agreement and/or the rights and liabilities of the Parties, thereunder, and the Parties thereunder, the Parties shall endeavour to settle such disputes/differences amicably, failing which the dispute/difference shall be settled in accordance with the provisions of the Arbitration and Conciliation Act, 1996 of any statutory re- enactments or modification thereof. Sole arbitrator to be appointed with mutual consent of both the Parties. The seat and venue of Arbitration shall be Mumbai. The language of the Arbitration shall be English. The Award passed by the Arbitrator shall be final and binding upon the parties herein.”
9. On 11.10.2024, SEPL through Petitioner No.2 sent a notice
of termination of the JVA to RWCL and RBIPL (subsidiary
company of RWCL) which is alleged to have been incorporated
to compete with the joint venture entity RWIPL in breach of
the non-compete covenant, namely Article 24.1 of the JVA.
The grounds of termination set out are inter alia as under:
(a) Incorporation of RBIPL by RWCL to compete with the
joint venture entity RWIPL (constituted by SEPL and
RWCL) in contradiction of Article 24.1 of the JVA.
(b) Business loss and opportunity due to rejection of
projects on grounds of technical incompetence.
(c) In addition to floating RBIPL as a competitor of the joint
venture RWIPL, RWCL caused inordinate delay in
giving inputs for the technological viability of various
big projects and subsequently used such delay to reject
such projects for lack of technical competence. This
was done with the ulterior motive of promoting and
propagating RBIPL which had been incorporated in
contravention of the JVA itself.
(d) Under the MoU, SEPL procured decanter systems from
RWCL worth Rs. 15,27,72,420/- as on 25.05.2023 to
supply them to JWIL (the main contractor on Municipal
Corporation of Greater Mumbai's Bhandup project). As
per mutual agreement, the government dues and costs
thereof were payable by RWCL. Pursuant to the same,
SEPL vide its email on 06.09.2024, subsequent
reminders on 19.09.2024 and 20.09.2024 and final
reminder on 30.09.2024 raised a claim of Rs.
4,24,35,647/- towards receivable liability from RWCL
to SEPL for the costs, taxes, liabilities and interest
incurred by SEPL on behalf of RWCL.
Quoting these infractions, SEPL issued the termination
notice of the JVA and called upon RWCL to pay Rs.
20,00,00,000/- for business loss and a sum of Rs.
4,24,35,647/- under the MoU.
10. Another notice of the same date was issued by SEPL to RWCL
with regard to the aforesaid claim of Rs. 4,24,35,647/- plus
applicable taxes, interest, etc. under the MoU, which was
disputed by RWCL and Respondent No.2.
11. In their reply, RWCL and Respondent No. 2 disputed the
aforesaid termination notice vide letter dated 28.10.2024,
countering the allegations of outstanding dues raised by
SEPL and called upon the latter to amicably settle the
dispute. RWCL further mentioned in the reply that the
dispute is directly linked with the operation and management
of the License Agreement dated 30.01.2019 and, therefore,
the dispute resolution clause of the said License Agreement
would be applicable to the dispute.
12. In the backdrop of the aforesaid disputes, SEPL issued
notices of arbitration dated 28.11.2024 under Article 43 of
the JVA and Clause 9 of the MOU respectively. In reply to the
said notices, RWCL while acknowledging the disputes,
reiterated its stance that the said disputes were intrinsically
connected to the License Agreement dated 30.01.2019 and
that any dispute resolution via arbitration was covered under
Clause 12.1 of the said agreement in accordance with the law
of the Republic of Korea. The said clause reads as follows:-
“If after 30 days of consultation, the Parties have failed to reach an amicable settlement, on any and all disputes or differences arising out of or in connection with this Agreement or its performance, such disputes or differences shall be referred to arbitration in Seoul which shall be conducted in accordance with the Law of Republic of Korea which governs and protects the interest of the Republic of Korea and Indian parties respectively and any statutory modification and re-enactment thereto for the time being in force all the parties thereto irrevocably agree that the decision of the Arbitrator(s) shall be final and binding upon the parties hereto and the judgment or arbitration award may be entered in any court of competent jurisdiction. The language of the Arbitration shall be English.”
13. In these circumstances, Petitioners have taken out the
petitions under Section 11 of the Arbitration and Conciliation
Act, 1996 (“1996 Act”) for referring the disputes to
arbitration and appointment of an arbitrator under Article 43
of the JVA and Clause 9 of the MoU respectively.
14. In their counter affidavits to the aforesaid petitions,
Respondents, while not denying that disputes have arisen by
and between the parties under the JVA and MoU, contended
that Petitioners had not referred the said dispute for an
amicable resolution as contemplated in the arbitration
clauses. They have also taken a specific plea that these
agreements are governed by the License Agreement dated
30.01.2019 as their mother agreement. Accordingly, the
dispute resolution clause therein, namely Clause 12.1,
providing for arbitration in Korea would prevail. It is further
alleged that there was a breach of the exclusivity clause
under the License Agreement. RWCL has also issued a notice
of arbitration dated 08.08.2025 under Clause 12 of the said
License Agreement for arbitration in Korea. It was also argued
that RBIPL, being a non-signatory to the aforesaid
agreements, is not bound by the arbitration clause.
15. Initially, we had referred the matter for an amicable
resolution of the dispute via mediation. Learned Senior
Counsel Mr. C.U. Singh and Mr. Sudhanshu Choudhari
appearing for the parties informed that though some progress
was made during mediation, the parties finally could not
arrive at an amicable resolution.
16. Given the situation, we have considered the matter on merits.
While both parties do not dispute the existence of the
arbitration agreements namely the JVA and MoU in respect
whereof the disputes have arisen, Mr. Choudhari, for the
Respondents, argued that the said agreements are
intrinsically intertwined with the mother agreement i.e.,
License Agreement dated 30.01.2019 and the dispute
resolution clause therein, namely Clause 12.1, providing for
arbitration in Korea, would govern such disputes. He further
asserted that his client has already issued a notice alleging
breach of the exclusivity clause in the License Agreement and
has already issued a notice invoking arbitration on
08.08.2025 under the said License Agreement in Korea. He
also contended that RBIPL is an independent non-signatory
entity and cannot be bound by the arbitration agreements.
17. In rebuttal, Mr. Singh submitted that the JVA and MoU are
independent of the License Agreement. In support thereof,
he referred to Article 25 of the JVA and Clause 10.8 of the
MoU. He also asserted that RBIPL is a wholly owned
subsidiary of RWCL and Respondent No.2 and his daughter
are the directors of RBIPL. It was incorporated in
contravention of Article 24.1 of the JVA to unfairly compete
with the joint venture entity RWIPL and hence is a necessary
party to the arbitration agreement.
18. Having considered the rival submissions at the Bar, we find
that the existence of the arbitration agreements governing
disputes under the JVA and MoU is admitted. Furthermore,
Article 25 of the JVA states that the agreement is an entire
agreement between the parties in respect of the subject
matter thereof and supersedes all prior agreements, if any,
between them with respect thereto. Similarly, Clause 10.8 of
the MoU cancels and supersedes any and all prior
agreements as to the subject-matter.
19. Section 11(6-A) of the 1996 Act prescribes the principle of
minimal judicial intervention by restricting the scope of
inquiry to prima facie existence of the arbitration agreement.1
Once the prima facie existence of an arbitration agreement is
1In re: Interplay Between Arbitration Agreements under the Arbitration and Conciliation Act, 1996 and the Indian Stamp Act, 1899, (2024) 6 SCC 1. 11
adduced before the Referral Court, it ought to appoint an
arbitrator and refer the parties to arbitration.
20. Admittedly, the existence of the agreements is not in dispute.
What is contended is that the JVA and MoU spring from the
mother agreement, namely License Agreement, and have no
independent existence. As such, the dispute resolution
clause, namely Clause 12.1 of the mother agreement,
envisaging arbitration in Korea would override the dispute
resolution clauses in the subsidiary agreements.
21. Having examined the terms of the License Agreement, JVA
and MoU, we note that the License Agreement deals with
grant of multiple licenses by RWCL to SEPL and/or its
affiliates; JVA creates a joint venture company in India
namely RWIPL to carry on business activities in supply,
installation, operation and maintenance of latest generation
sewage treatment plants and other liquid procession
products and equipment under the brand name
‘ROTHWELL’; and MoU is an arrangement between SEPL and
RWCL by which SEPL would render liaison and other services
on behalf of RWCL with JWIL and Municipal Corporation of
Greater Mumbai. Thus, the License Agreement, JVA and MoU
prima facie operate in different fields and the disputes arising
exclusively under the JVA and MoU are amenable to the
dispute resolution clauses engrafted therein and not the
clause in the License Agreement. We are further fortified to
come to such conclusion with reference to Article 25 of the
JVA and Clause 10.8 of the MoU which inter alia provide that
the said agreements are exclusive in respect of the subject
matter thereof and supersede all or any prior agreements. Mr.
Choudhari’s argument that the disputes pertaining to the
JVA and MoU cannot be adjudicated in isolation and overlap
with claims under the License Agreement in respect whereof
his clients have already raised a dispute for arbitration in
Korea, would fall within the jurisdiction of the arbitrator vis-
à-vis the scope and ambit of disputes amenable to arbitration
under the JVA/MoU, and cannot constitute a ground to
refuse a reference at the threshold.
22. Similarly, the other issue that RBIPL is an independent non-
signatory entity which is not bound by the arbitration
agreement is a contentious one as RBIPL is a wholly owned
subsidiary of RWCL (a signatory) and is alleged to have been
incorporated by RWCL in derogation of the terms of the JVA.
Given this situation, such issue needs to be relegated to the
arbitrator for appropriate adjudication.
23. In light of the above, we allow the present arbitration petitions
and appoint Hon’ble Mr. Justice Ramesh Deokinandan
Dhanuka, Former Chief Justice of Bombay High Court as the
Sole Arbitrator. The Arbitrator shall have the liberty to fix his
own remuneration/fees.
24. There shall be no order as to costs in these petitions.
..…………....................CJI. (SURYA KANT)
…..…………....................J. (JOYMALYA BAGCHI)
..…..………......................J. (V. MOHANA) NEW DELHI October 08, 2026