MIS INDIAN MAIZE AND CHEMICALS LTD. v. STATE OF U.P. AND ORS.
vidhipandit.com/case/sc-1997-1-216-219
Machine-read from a scanned report. Check the printed page before citing. Report an error.
Report as printed — headnote and judgment are not separated on this page
A
JANUARY 13, 1997 B
Indian Electricity Act, 19)0:
Sick lndusuial Companies (Special Provisions) Act, 1985 : Section c 22( 1).
E/eclliciry supply--Agreement between petitioner and respo11de11t Board:-Outsta11ding payment-Witli a view to avoidi11g disco111iectio11 ~
v petitioner agreeing to make payment i11 12 monthly i11stalments-Board agreed D for same and gave reco11nection subject to the petitioner paying the agreed -t- amount--Petitio11er paid one instalment a11d thereafter committed • defau It-Anticipated disc01mectio11-Writ filed by petitionet-Seeking direc- tio11 not to recover outstanding amount-Ground that as it was a sick industry and its claim for rehabilitation was pending before B.I.F.R., thenfore, no action could be taken in that behalf-High Court refused to gr<ult relief-Ap- E peal before Supreme Court-Held under the Indian Electricity Supply Act, .. one of the conditio11s is that conti11ued paymellt of the price of electrical e11ergy :mpplied by the Board is a co11dition for the conti~ued supply-Default • committed in the payment thereof entails .disconnection of the supply-Since the petitioner had committed default and as a condition for re-connection, r- F agreed t~ pay the amoullt in instalments, he is liable to comply with the undertaking given for supply of electrical energy--lt is not elltitled to w.·k any declaratio11 or direction from the Court that since the matter is pending before the BIFR, he would be entitled to the supply of elecl1ical energy without the compliance of the c01responding obligation of payment under regulations or of the contract under the Indian Electdcity Supply Act. G C.E.S.C. Ltd. & Ors. v. Bowrech Cotton Mills Co. Ltd. & Ors., [1993) Supp. 1 SCC 451, held inapplicable. • Modi Spinning & Weaving Mills Co. Ltd. v. U.P.S.E.B. & Ors., AIR H (1992) All. 247, referred to. 216
) . ' M/S. INDIAN MAIZE AND CHEMICALS LTD. v. STATE 217
--~ CIVIL APPELLATE JURISDICTION: Special Leave Petition (C) A No. 1421of1997.
From the Judgment and Order dated 2.6.7.96 of the Allahabad High Court in W.P. No. 2109 of 1996.
R. Santhanam, Rajendra Singhvi and Ashok Kumar Singh for the B
-· Petitioner.
The following Order of the' Court·was delive~ed:
.. Delay condoned. •, c The petitioner is, through this petiticin, assailing the correctness of the order of the Allahabad High Court, Lucknow Bench, made on July 26, 1996 in Writ Petition No. 2109 of 1996. The petitioner got the electricity '· connection from the respondent-U.P. State Electricity Board on February 6, 1990 for the Supply of electric energy of 1650 KVA The petitioner had D -4' executed an agreement and also complied with the formalities for the supply of electricity in terms of Indian Electricity Act, 1910. The petitioner claimed the rebate on the basis that he had established the industry in an undeveloped area but we are not concerned with that controversy. Admit- · tedly, a sum of Rs. 49.95 lacs was due from the petitioner. On a demand ·raised· by the Board on June 4, 1996 in that behalf, the petitioner ap- E proached the High Court. The petitioner, with a view to avoid disconnec- tion had agreed with the Board on June 10, 1996 for payment of above outstanding amount in U monthly instalments and the Board had agreed for the same and given re-connection subject to the petitioner paying the ~ amount as agreed. The petitioner after depositing one instalment, com· F · mitted default in the payment. Since the petitioner anticipated disconnec- tion, it approached the High Court for the direction not to recover the amount putting forth the plea that the petitioner is a sick industry and his claim for rehabilitation was pending before B.I.F.R. and, therefore, no action could be taken in that behalf. The High Court has refused to grant the relief by the impugned Order dated June 26, 1996. Thus, this special G leave petition. -,_ Learned counsel for the petitioner has contended that the controver- sy is covered by the judgment of this Court in C.E.S.C. Ltd. & Ors. v. _, Bowrech Cotton Mills Co. Ltd. & Ors., [1993) Supp. 1 SCC 451. Therefore, , H
p. 218
A the High Court was not right in relying upon that Court's earlier judgment . I in Modi Spinning & Weaving Mills Co. Ltd. v. U.P.S.E.B. & Ors., AIR {1992) All. 247. We find that the contention raised by the learned counsel is not correct in law. It is seen that in CESC Ltd. case, this Court had expressly left open the question of the undertaking given and the default committed and fulfilment thereof since that question was not raised in the High Court B as expressly mentioned in paragraph 3 thereof. With regard to the delayed payment, surcharge etc. the direction issued by the High Court was modified in paragraph 4 and direction was given to pay the amount in instalments as envisaged in paragraph 4 of the judgment. As far as the arrears are concerned, since the first question was not considered, this C Court had held that since the matter was pending before the BIFR it .. needed to be considered by the BIFR itself. . . It is seen that Section 22(1) of the Sick Industrial Companies {Special Provisi?ns) Act, 1985 envisages as under:
D "22 Suspension of legal proceedings, contracts, etc. -(1) Where in respect of an industrial company, an inquiry under Section 16 is pending or any scheme referred to under Section 17 is under preparation or consideration or a sanctioned scheme is under implementation or where an appeal under Section 25 relating. to E an industrial company is pending, then, notwithstanding anything contained in the Companies Act, 1956 (1 of 1956), or any other law or the memorandum and articles of association of the industrial Company or any other instrument having effect under the said Act or other law, no proceedings for the winding up of the industrial F :, company or for execution, distress or the like against any of the j properties of the industrial company or for the appointment of a ' i receiver in respect thereof (and no suit for the recovery of money
1 , or for the enforcement of any security against the industrial com- pany or of any guarantee in respect of any loans or advance granted to .the industrial company) shall lie or be proceeded with further, except with the consent of the Board or, as the case may be, the appellate Authority.''
A reading of the above section would indicate that. when the proceedings are pending before the BIFR in respect of any matter referred to therein for inquiry by the Board, the proceedings or order of execution,
M/S. INDIAN MAIZE AND CHEMICALS LTD. v. STATE 219
distress or the like would be stayed until the proceedings get concluded before the BIFR or would not be proceeded without the leave of the Board or Appellate Authority. It is seen that under the Indian Electricity Supply Act, one· of the conditions is that continued payment of the price of electrical energy supplied by the Board is a condition for the continued supply and the default committed in the payment thereof entails discon- B nection of the supply of electrical energy, except in accordance with the procedure prescribed under the contract or the regulation issued under the Indian Electricity Supply Act. Execution connotes pre-existing decree. It is true that any action for realisation etc. pending decision by BIFR or without its permission is prohibited. Enforcement of compliance of the obligation under the contract or regulation for supply of electrical energy by ordering payment of electrical energy is not and cannot be considered to be execution of a decree. Execution of the decree presupposes existence of a decree of a competent court and the dec.ree-holder should take steps to have it executed pending proceeding before BIFR. There is no decree of court. Since the petitioner had committed default and as a condition for re-connection, agreed to pay the amount in instalments, he is liable to comply with thi; undertaking given for supply of electrical energy. The petitioner committed default in that behalf. So, it is not entitled to seek any declaration or direction from the Court that since the matter is pending before the BIFR, he would be entitled to the supply of electrical energy without the compliance of the corresponding obligation of payment under regulations or of the contract under the Indian Electricity Supply Act. It is, therefore, not correct to say that since the ·proceedings are pending before the BIFR, the electricity is required· to be supplied to the consumer without compliance of the conditions. It is then sought to be contended that. the authorities· may take coercive steps to recover the arrears. At this state, we need not go into the question.
The special leave petition is accordingly dismissed.
T.N.A. Petition dismissed.