LAKSHMICHAND & BALCHAND v. STATE OF ANDHRA PRADESH -,,--

vidhipandit.com/case/sc-1987-1-108-113

Supreme Court of India (SC) · decided (year only) · R.S. PATHAK and G.L. OZA · judgment

Decision dates shown here are day-precision where the judgment's own text states a date the extractor is confident in, and year only otherwise -- never a fabricated day. See the editorial policy for how dates are extracted.

[1987] 1 S.C.R. 108

Headnote — Supreme Court Reports (editorial summary, not part of the judgment)

Held

I. The Court has the power to allow a set off in certain B I circumstances even in cases which do not strictly fall within the terms of Order 21, Rule IS of the Code of Civil Procedure. [Il2B] . . I... . Bhoganadham Seshaiah v. Budhi Veerabhadrayya (died) & Ors., r'" -AIR 1972 Andhra Pradesh 134, approved.

Reporter's headnote (continued) and case details

A •

NOVEMBER 5, 1986

B

Civil Procedure Code, 1908-0rder 21, Rule 18-Power of the y Court to allow set off-When is a claim founded on doctrine of equit- able set off. I c The appellant...:ontractor entered into two agreements with the -~ _,,.. respondent State for carrying out certain road repairing works. Clause " 68 of the agreement provided for preparation or the final bill of the contractor after taking into account amounts received by him earlier, while clause 71 permitted the State to retain or deduct money due under the contract from an amount due to the contractor under any other contract. While the work was in progress the contractor made certain claims in respect of loss suffered on account of delay, escalation of rates and other heads. The arbitrato1· held the contractor entitled to Rs.99 lacs. The civil court refused to pass a decree in terms of the award. The High Court on appeal allowed the claim to the extent of Rs.16 lacs together with interest. The co111tractor claimed recovery of decretal amount with interest in terms of the award and cost of execution pro- ceedings. The respondent State contested the claim contending that a sum of Rs.22 lacs was recoverable from the appellant and claimed adjustment against the amount due under the decree. The Executing Court held the respondent State entitled to set off.

F .... In the revision petition before the High Court it was contended for the appellant that the respondent State was not entitled to set off in execution proceedings, and that the sum of which adjustment was sought ~. consisted of (a) an amount claimed by respondent State as due to it upon preparation of the final bill in respect of the contracts covered by the ..\ award, and (b) an amount claimed by the respondent State under a G separate contract on the ground that the appellant bad committed a breach of that contract. The High Court having regard to cl. 68 of the agreement found the respondent State entitled to set off so far as the first claim was concerned. It justified the second claim also by reference to cl. 71 of the contract hut held that adjustment claimed could not be ..,.. made against the decretal amount hut must await determination upon H the arbitration.

108

LAKSHMICHAND v. STATE OF ANDHRA PRADESH 109

-,· In this appeal by special leave it was contended that Order 21, A 1 Rule 18 of the Code of Civil Procedure, under which a set off can he claimed, does not apply in terms to the present case.

Allowing the appeal in part, the Court,

2. The respondent State's claim to adjustment of the amount due c to it upon the preparation of the final bill is covered by cl. 68 of the contract. What was awarded to the contractor under the decree was an amount relating to a part only of the work entrusted to him. The con· tract was still in the process of execution. Any amount claimed by him for such work was subject to a final settlement of account on the pre- D paration of the final bill. The right to payment depended on the terms of the contract. Any payment made while the contract was still being workecl ont was in the natnre of a provisional payment. It was always sobject to adjnstment against amount,s found doe on preparation of the final bill. Such adjustinent was implied in the very terms or the COD· tract. The High Court was, therefore, right in holding that the amount E claimed by the State Government on this count was entitled to be set off against the decretal amount claimed by the contractor. [1!2C El

3.1 The claim to adjustment of the amount claimed on breach of ·, another contract is founded in the doctrine of equitable set off but ['- there is no e>idence on record to bring the case within the operation of the doctrine. It is not a case where cross demands rise out of the same ,..). transaction, or the demands are so connected in their natnre and circum- stances that they can be looked upon as part of one transaction. [I l 2F GI

3.2 The benefit of cl. 71 of the contract can be claimed only if the amount sought to. he retained is an ascertained sum, an amount which G · can be readily adjusted against the amount payable under the other contract. In the instant case, the amount sought to be adjusted had yet to be determined. as a liability against the contractor. The decision of the High CIHlrt eannot, therefore, be sustained. [1!2GH, l !3A)

CIVIL APPELLATE JURISDICTION: Civil Appeal No. ~083 H of 1986

110 SUPREME COURT REPORTS (1987] I S.C.R.

A From the judgment and order dated 13.4.1984 of the Andhra Pradesh High Court in C.R.P. No. 3072 of 1983.

Dr. Y.S. Chitale, G.N. Narayan and N. Nittarfor the Appellant.

T.S. Krishnamurthy Iyer, T.V.S.N. Chari and Ms. V. Grover for B the Respondent. y

Judgment

The Order of the Court was delivered by

PATHAK, J. This appeal is directed against the judgment and order of the High Court of Andhra Pradesh disposing of a revision ~- ,,... c petition filed by the Appellant in execution prbceedings.

The Appellant is a contractor, who entered info two agreements _:... with the Government of the State of Andhra Pradesh for providing B. T. Macadam wearing coat and seal coat along two stretches of the Hyderabad-Vijayawada Na.tional Highway. While the work was in D progress, the contractor made certain claims in respect of the loss suffered on account of delay, escalation of rates and other heads. The claims were referred to arbitration. On September 4, 1979 the Ar- bitrator held the contractor entitled to a sum of Rs.99,00,000 under five heads of claim. The contractor applied to the Civil Court for making the award a rule of the Court while the State Government E prayed for setting aside the entire award. The Civil Court set aside the award and refused to pass a decree in terms of the award. 'The con- tractor appealed to the High Court, and on April 19, 1982 the High Court allowed the appeal to the extent of one of the claims only, the .... claim being for loss of profit in the sum of Rs. 16,00,000 together with interest. The appeal was dismissed in respect of the other heads of I F claim. /"

For the realisation of the amount due under the decree the con- l. tractor filed Execution Petition No.48 of 1982 before the V Additional Judge, City Civil Court, Hyderabad claiming recovery of Rs.16,00,000 towards the decretal amount, Rs.7,80,000 towards interest in terms of G the award up to the date of the execution petition and Rs.8,691 to- wards costs of the Execution Petition. The State Government filed objections, contending inter alia that a sum of Rs.22,91,332 was recov- erable by it from the contractor and claimed adjustment against the amount due to the contractor under the said decree. It urged that after adjusting the amount due to the State Government the balance pay- H able to the contractor would stand reduced to Rs.76,667. This sum

LAKSHMICHAND v. STATE OF ANDHRA PRADESH [PATHAK, J.Jl l l

together with the other deposits of the contractor with the Govern- A ment and refundable to him, viz. Rs.3,92,236 was deposited in the Executing Court. The contractor withdrew the amount without pre- judice to his rights to contest the adjustment. The Executing Court held that the State Government was entitled to set_ off-the amounts claimed by it, and accordingly adjourned· the Execution Petition for further proceedings. B J. The contractor filed a revision petition before the High Court and contended that the State Government was not entitled to claim I.. _adjustment in execution proceedings. It was pointed out that the sum r of Rs.22,91,332 of which adjustment was sought by the State Govern- ment against the amount for which the contractor had taken out execu- tion, consisted of (a) an amount of Rs.10,21,800 claimed by the State c --f- Government as due to it upon the preparation of the final bill in respect of the contracts covered by the award and (b) an amount of Rs. 12,69 ,532 claimed by the State Government under a separate con- tract on the ground that the contractor had committed a breach of that contract. The contractor disputed both claims. He contended that the D final bill in respect of the earlier contract had been prepared in his · absence and that he challenged the inclusion of several items in that bill. In regard to the latter amount he urged that he was not guilty of· any breach of contract.

The High Court has found that so far as the first claim to adjust- E ment was concerned the State Government was justified in making·it because the arbitr_ation was effected while the work was still in prog- ress and the contract was in the process of execution by the contractor, and having regard to clause 68 of the agreement final payment had to be made to the contractor after taking into account the amount which had been received by him earlier. The seConct claim to adjustment was F made by the State Government under another contract, and the High Court justified that claim hy reference to clause 71 of that contract, which permitted the Government to retain or deduct money due under the contract from an amount due to the contractor under any other contract. However, it held that the adjustments claimed by the State Government could not be made against tl>e decretal amount but must G . await determination upon due arbitration.

Learned counsel. for the Appellant contends before us that the State Government is not entitled to a set off at all because, he says, a set off can be claimed only under Order 21 Rule 18 of the Code of Civil Procedure and that provision does not apply in terms to .the present H

112 SUPREME COURT REPORTS [1987] l S.C.R.

A case. Learned counsel for the respondent urges, on the other hand, that the power of the Court extends to granting an equitable set off in appropriate cases, and the High Court was therefore justified in mak- ing the order which it did.

We have no doubt that in certain cases the Court has the power to B allow a set off even in cases which do not strictly fall within the terms of Order 21 Rule 18 of the Code. A Full Bench of the Andhra Pradesh High Court has discussed the matter in Bhoganadham Seshaiah v. Budhi Veerabhadrayya (died) and Others, AIR [!972) Andhra Pradesh !34 and has examined at some length the circumstances in which such I set off may be granted. The facts before us, however, call for a some- - .A, C what different consideration. So far as the first claim to adjustment is concerned, the matter is covered by clause 68 of the contract. What was awarded to the contractor under the decree was an amount relat- ing to a part only of the work entrusted to him. The contract was still in the process of execution. Any amount claimed by him for such work was subject to a final settlement of account on the preparation of the D final bill. The right to payment depended on the terms of the contract. Any payment made while the contract was still being worked out was in the nature of a provisional payment. It was always subject to adjust- ment against amounts found due against the contractor on preparation of the final bill. Such adjustment was implied in the very terms of the contract. Therefore, in regard to the adjustment claimed by the State E Government on the first count the High Court is right, in our opinion •. in holding that the amount claimed by the State Government, as de- termined on arbitration, was entitled to a set off against the decretal amount claimed by the contractor, and that payment of the decretal amount was to be subject to such adjustment.

F In regard to the claim to adjustment on the second count the __,~ position is more controversial. The claim is founded in the doLtrine of equitable set off, but we do not find evidence before us to bring the case within the operation of the doctrine. It is not a case where cross demands rise out of the same transaction or the demands are so con- nected in their nature and circumstances that they can be looked upon G as part of one transaction. Nor can assistance be derived from clause

71. The benefit of that provision can be claimed only if the amount sought to be retained is an ascertained sum, an amount which can be readily adjusted against the amount payable under the other contract. Here, the amount sought to be adjusted has yet to be determined as a liability against the contractor. It has been disputed by the appellant. H Accordingly, clause 71 cannot be invoked. In the result, the decision

LAKSHMICHAND v. STATE OF ANDHRA PRADESH (PATHAK. J.( l l3

of ine High Court in respect of the adjustment of Rs.12,69;532 cannot A be sustained.

In the circumstances, the appeal is allowed in part, the judgment and order of the High Couc:t is modified in so far that while the adjust- ment claimed by the State Government on the basis of the final bill relating to the contract covered by the award is maintained, the direc- B ·1 ' tion in respect of the. adjustment of 1he claim made under the other contract is 'set aside. The parties will bear their oWTYcosts .

. P.S.S. Appeal allowed. r~- c

-(

Report an error in this judgment →

Contains information from the Indian High Court / Supreme Court Judgments dataset, licensed under CC-BY-4.0